# Who Buys the Capacity? How Grid Operators Are Deciding Whether Data Centers Bring Their Own
- URL: https://www.aixenergy.io/who-buys-the-capacity/
- Published: 2026-11-27T14:28:37.000Z
- Updated: 2026-11-27T14:28:37.000Z
- Description: Answering the same federal order, America's grid operators have split on whether a new data center's demand belongs in the capacity everyone buys together, or is left for the data center to cover.
- Author: Brandon N. Owens
- Tags: Business & Finance, Policy & Regulation

Article Summary

0:00

/31.764898

1×

- Grid operators answering FERC's June large-load orders have split on whether a new data center's demand belongs in the capacity that all customers buy together.
- ISO New England would require new capacity for firm service and exclude interim and non-firm large loads from its Installed Capacity Requirement, with detailed rules due in 2027.
- SPP and MISO offer non-firm services with price triggers of $25 and $100 per megawatt-hour that carry no capacity obligation, while firm load still needs accredited capacity.
- In PJM, FERC rejected an interim adequacy service in October, and the board declined consumer advocates' request to postpone the December 9 auction, citing reliability and state authority over retail costs.

---

Bidding opens on December 9 in the capacity auction that will set what the largest wholesale market in America pays to keep the lights on from June 2029 to May 2030\. On November 18, consumer advocates from several of its states asked for it to be postponed until forecast data center demand could be taken out of it. On November 25 PJM Interconnection's board said no. Its chair wrote that PJM cannot delay the auction without an order from the Federal Energy Regulatory Commission, that the date had been fixed since November 2024, and that removing demand to lower the clearing price would mean buying less capacity in a region already short of its reliability target.[1](#fn1)

The exchange is about one auction, but the question behind it is now being asked everywhere that grid operators run markets. When a data center of several hundred megawatts asks to connect, the familiar issue is whether the wires can carry the load. The newer issue is who pays for the power plants that must be standing by when that load and everyone else's peak at the same time. In November, in filings answering the same federal order, the operators gave strikingly different answers.

## From a wires question to a capacity question

On June 18, 2026, FERC opened show-cause proceedings against each of the regional operators it regulates, finding that their tariffs appeared to lack clear rules for large loads and for loads co-located with generators. The orders also required an informational report on resource adequacy, the planning discipline that keeps enough accredited supply on hand for peak demand.[2](#fn2) The responses arrived between November 13 and November 20\. Most of their pages concern study queues, deposits and interim service while upgrades are built. A smaller number of pages decide something with larger consequences for household bills: whether a new data center's demand is counted in the capacity that everyone buys together, or is set aside and left to the data center to cover.

Four approaches stand out. They differ less in their mechanics than in where they put the risk that a forecast is wrong.

## New England: bring new capacity, or stay off the books

ISO New England has the least data center load of any of the large markets, and says so. Its November 13 filing notes that large loads "have yet to materialize" in the region.[3](#fn3) It has nonetheless proposed the most explicit separation. A large load, defined as a commercial or industrial customer at a single site with gross peak demand of 50 megawatts or more, could take one of three services. Firm Contract Demand Service carries the same priority as any other firm load, but only if the customer designates "sufficient new capacity resources" to match the firm amount. Until that new capacity is built, the load takes interim service instead. A third option, non-firm service, needs no new capacity at all.[3](#fn3)

Loads on interim or non-firm service would be "excluded from the calculation of the Installed Capacity Requirement and related values," the quantity New England's capacity market is designed to buy.[3](#fn3) In exchange, those loads would be redispatched, meaning told to reduce consumption or raise their own generation, whenever the local energy price reaches $250 per megawatt-hour, a level the operator says the region has reached in only about 1% of hours.[4](#fn4) Applications would open on June 1, 2027, with service from June 2028\. The rules that give "bring your own new capacity" its substance, including what counts as new and how designated resources are accredited, are still to be written with stakeholders and filed in 2027.[3](#fn3)

The effect is that existing customers do not buy capacity for a new data center until the data center has paid for some itself. The cost is a slower or less certain path to firm service for the customer.

## SPP: a flexible service with no capacity attached

Southwest Power Pool has taken a different route to a similar place. Its Price Adaptive Load Service, filed on November 19 in docket ER27-578, lets a large load buy non-firm transmission for terms of one to ten years. The load's market bids are capped at $25 per megawatt-hour, so it stops drawing power whenever prices rise above that level. The service "carries no resource adequacy obligation," and SPP's filing says such loads are excluded from its load forecasts. Firm loads, by contrast, "must be supported by accredited capacity."[5](#fn5) SPP chose the cap after simulating ten 200-megawatt flexible loads. Raising the cap from $20 to $25 lifted their real-time load factor from 45% to 60%, while the effect on average prices for other customers grew faster above $25.[5](#fn5) Launch is targeted for the second quarter of 2028.

A companion filing, ER27-577, addresses a different cost: the wires. It would cap the network upgrade cost spread across SPP's regional rates for any new delivery point at the lesser of $500,000 per megawatt or $25 million, and assign the excess to the customer that asked for it, recovered over up to 40 years. SPP notes that its tariff currently has no such limit, regardless of the cost relative to the load or "whether the load materializes."[6](#fn6) The cap is a transmission rule rather than a capacity rule. It belongs in the same conversation because it answers the same question for a different asset: if the load does not arrive, who is left holding the bill.

## MISO: forecasts first, with a non-firm exit

The Midcontinent Independent System Operator still builds its capacity requirement mostly from the bottom up. Market participants submit peak-load forecasts for each balancing area, with documentation of their methods, and MISO converts them into a Planning Reserve Margin Requirement by adding transmission losses and a reserve margin set by loss-of-load studies.[7](#fn7) Whatever data center load a utility puts in its forecast, its customers buy capacity for.

MISO's November 16 filing for Grid Responsive Integration Transmission Service, docket ER27-527, adds an alternative. A large load can split itself into a firm slice and a non-firm slice. The firm slice stays in the peak forecast and must procure Zonal Resource Credits, MISO's unit of accredited capacity. The non-firm slice "may be excluded from the obligation to procure Zonal Resource Credits" and drops out of the forecast. It is interrupted whenever its local price exceeds $100 per megawatt-hour, which MISO says would still have allowed service in more than 95% of hours, and in full whenever MISO declares a capacity advisory in its area.[8](#fn8) A customer that fails to interrupt faces remote disconnection by its transmission owner, penalties and possible termination. MISO says it could implement the service no earlier than January 1, 2029.[8](#fn8)

Not every stakeholder accepts the trade. A coalition of generators argued in MISO's working group that all load, firm or not, is ultimately served by resources supported by capacity revenues, and that excluding it from the auction "removes it from the demand that sets capacity prices."[9](#fn9) MISO's answer is that the price cap and the advisory trigger keep non-firm load from competing with other customers "at the times when Resource Adequacy is under pressure."[8](#fn8)

## The largest market: an auction under protest

PJM proposed something close to the New England model, and FERC rejected most of it. In August it asked FERC to approve an Interim Resource Adequacy Service, under which new large loads would face curtailment during shortages unless their load-serving entity designated new capacity at least equal to the load's peak, along with rules to exclude eligible new large loads from the auction's demand curve starting with the 2029/2030 delivery year. On October 9 FERC accepted PJM's definition of a large load and its new registry of them but rejected the rest. It found that parts of the proposal appeared to place obligations directly on retail customers and to set a retail rate, matters outside its authority, and that PJM had not shown other parts to be just and reasonable. FERC offered guidance should PJM refile.[10](#fn10)

That left the December auction to run on PJM's 2026 load forecast. Monitoring Analytics, PJM's independent market monitor, estimated on November 12 that including existing and forecast data center demand had already raised capacity costs by $29.4 billion across the auctions held so far. Leaving most forecast data center load in the December auction, it wrote, "effectively ensures that the auction will clear at the maximum price and add another $5 to $10 billion of data center related costs to all customers." It recommended removing forecast data center load from the auction and procuring for it separately through bilateral contracts or a backstop auction.[11](#fn11) The monitor also reported that the 2028/2029 auction cleared 6,831.3 megawatts short of the required reserve level.[11](#fn11) Eight consumer advocate offices cited that analysis on November 18 in asking the board to seek a delay.[12](#fn12)

The board's reply rested on reliability and on jurisdiction. It said a lower price produced by removing demand "would necessarily be the consequence of committing fewer capacity resources." It noted that the auction carries a price cap well below the top of the approved demand curve, the same cap used in the previous three auctions. And it said that allocating wholesale costs to data centers is generally for retail regulators, not PJM. The board added that it is considering delaying the following auction, due in May, to reform the market, and has suggested a move to a prompt auction held closer to delivery.[1](#fn1) A PJM spokesman described the choice to Utility Dive in plainer terms: PJM "must plan for the demand" that policymakers' and utilities' connection decisions create.[13](#fn13)

Table 1

Four answers to who buys the capacity

|                                              | ISO New England                                                                                                                      | SPP                                                                                                     | MISO                                                                                  | PJM                                                                                                        |
| -------------------------------------------- | ------------------------------------------------------------------------------------------------------------------------------------ | ------------------------------------------------------------------------------------------------------- | ------------------------------------------------------------------------------------- | ---------------------------------------------------------------------------------------------------------- |
| Where new large load sits in capacity demand | Firm load counted, matched by new capacity it designates; interim and non-firm load excluded from the Installed Capacity Requirement | Firm load needs accredited capacity; PALS load excluded from load forecasts with no adequacy obligation | Utility peak forecasts plus a reserve margin; non-firm GRITS slice may be excluded    | Included through the 2026 load forecast; proposed exclusion rejected by FERC on October 9                  |
| Flexible option and price trigger            | Interim and non-firm service, redispatched at $250/MWh                                                                               | PALS, bids capped at $25/MWh, terms of one to ten years                                                 | GRITS, interrupted above $100/MWh or in a capacity advisory                           | Interim adequacy service with curtailment, rejected on October 9                                           |
| Who carries a missed forecast                | Large load, through new capacity or curtailment                                                                                      | Large load, through curtailment; wires costs above the safe harbor assigned to the customer             | Customers of the forecasting utility for firm load; large load for the non-firm slice | All auction buyers, in the market monitor's view; the board cites the price cap and state retail authority |
| Screening and security                       | $50,000 fee, $150,000 study deposit, no-duplicate affidavit                                                                          | Financial security for directly assigned upgrade costs                                                  | Telemetry, remote disconnection and penalties for non-firm load                       | Large Load Registry accepted by FERC                                                                       |
| Status                                       | Filed November 13; applications from June 1, 2027; capacity rules due in 2027                                                        | Filed November 19; PALS targeted for the second quarter of 2028                                         | Filed November 16; service no earlier than January 1, 2029                            | 2029/2030 auction runs December 9 to 15; board weighing a delay to the May auction                         |

The New England, SPP and MISO proposals were pending before FERC at the time of writing. PALS is SPP's Price Adaptive Load Service; GRITS is MISO's Grid Responsive Integration Transmission Service. Sources: operator filings and FERC order cited in notes 3, 5, 6, 8, 10 and 11; PJM board letter (note 1).

## Two more variations

Two other operators show how wide the range has become. The New York Independent System Operator would test each large project against a resource adequacy impact standard. A project that degrades resource adequacy by more than 25 megawatts would receive only part of its request as firm service. Firm rights for the rest can come from a 15-year arrangement with a new capacity supplier, either on the same site or in the same capacity region. Its non-firm service would be curtailed at a nodal price of $200 per megawatt-hour.[14](#fn14) The California Independent System Operator has declined to make bring-your-own generation a condition of service. California has no centralized capacity market. Resource adequacy obligations sit with each load-serving entity and its regulator, and the operator argues that statewide forecasting and procurement are designed to anticipate new demand.[15](#fn15)

![Horizontal bar chart of the price at which non-firm large loads must reduce consumption under November 2026 proposals: SPP 25 dollars per megawatt-hour, MISO 100 dollars, NYISO 200 dollars and ISO New England 250 dollars.](https://storage.ghost.io/c/e3/c9/e3c9e740-20f7-4e9c-9a31-131fc1166819/content/images/2026/11/who-buys-the-capacity-figure1-price-triggers.png)

****Figure 1\. Where flexible data centers step back.** Price triggers for non-firm large-load service proposed to FERC in November 2026\. SPP's figure is a cap on the load's own bids; MISO also curtails in full during a capacity advisory. Sources: operator filings (notes 3, 5, 8 and 14).

## Who holds the risk

Set side by side, the approaches differ mainly in where the risk of a missed forecast lands.

Where forecast data center load sits inside the shared capacity requirement, as it does in MISO for firm service and in PJM today, existing customers share the cost of buying capacity for load that may arrive late or not at all. The monitor's estimate is the most quantified version of that concern. The same arrangement also means the capacity is bought before the load shows up, which is the reliability argument PJM's board makes for keeping it.

Where the load must bring its own capacity, as in New England's firm service and New York's partner arrangements, the risk shifts to the data center and the utility or retail supplier that serves it. The customer pays for capacity whether or not the computing business behind it thrives, and other customers are insulated from the purchase.

Where the load accepts non-firm service, as in SPP's PALS, MISO's non-firm slice and the interim and non-firm options in New England, the data center carries the risk of being switched off. Other customers then depend on that switch working. That is why each design pairs its price trigger with telemetry, control technology and penalties, and why stakeholders have asked how non-firm load will be represented in the probabilistic studies that set reserve margins.[9](#fn9)

## Screening the load that never arrives

Each of these designs depends on separating firm intentions from speculative ones, because demand that is counted but never built still raises the quantity an auction must buy. When supply is tight, the extra quantity moves the clearing price for every buyer, not just the one that overstated its needs.

The filings lean on money and paperwork. New England would require a $50,000 nonrefundable application fee, a $150,000 study deposit and an affidavit that the application is not duplicated elsewhere.[3](#fn3) New York scales study deposits from $100,000 to $300,000 with project size.[14](#fn14) Deposits deter casual requests, but they are small against the price of a capacity commitment, which is why the deeper argument is about whether forecasts should count load that lacks a signed service agreement, collateral or a contract with a supplier.

## What a buyer should bring

For a hyperscaler or developer, the practical lesson is that the same campus may need a different package in each region. In New England and New York, firm service will turn on accredited new capacity, and the definitions of "new" and of accreditation are still open. In SPP and in MISO's non-firm option, it will turn on a credible commitment to curtail, backed by metering and controls that the operator can verify. Everywhere, it will turn on a contract with the load-serving entity that serves the site, since that entity carries the capacity obligation in most designs and since FERC's October order and PJM's board both placed retail terms with the states.[10](#fn10)[1](#fn1)

## Questions for 2027

Much of the substance remains unwritten. New England's capacity rules are due in 2027, MISO's flexible service cannot start before 2029, and PJM is redesigning its capacity market while it decides how to refile. Commissions and boards will have to settle what counts as new capacity, and whether a contract for an existing plant that would otherwise retire qualifies. They will need to decide how non-firm load is modeled in loss-of-load studies and who audits that a curtailment actually happened. They will also need to settle, state by state, how wholesale capacity costs reach data center customers through retail tariffs, the point on which the PJM board and FERC both deferred to state authority.

None of these choices removes the underlying trade. Counting data center demand early buys reliability at the risk of paying for load that does not come. Setting it aside protects other customers at the risk of a shortfall if the load arrives without its own supply or fails to step back when asked. The December auction will show how one market is handling that trade for now. The filings from the rest show that the answer is unlikely to be the same everywhere.

Large-load tariffs and the proceedings that shape them can be tracked on the [AIxEnergy Map](https://map.aixenergy.io/?ref=aixenergy.io). For the study clocks and deposits in each operator's November filing, see [Six Answers on November 16](https://www.aixenergy.io/ferc-large-load-show-cause-scorecard/), and for what a refiled bring-your-own-capacity rule in PJM would need, see [Bring Your Own Capacity, Take Two](https://www.aixenergy.io/byoc-take-two-pjm-refiling/).

## Sign up for AIxEnergy Journal

The AIxEnergy Journal provides executive intelligence on AI infrastructure, data centers, electricity demand, electric grids, utilities, power markets, reliability, investment, and policy.

Subscribe 

Email sent! Check your inbox to complete your signup. 

No spam. Unsubscribe anytime.

## Notes

---

1. Paula Conboy, chair, PJM Board of Managers, letter to consumer advocate offices, November 25, 2026, [https://www.pjm.com/-/media/DotCom/about-pjm/who-we-are/public-disclosures/2026/20261125-board-response-to-the-consumer-advocates-letter-urging-postponement-of-upcoming-bra.pdf](https://www.pjm.com/-/media/DotCom/about-pjm/who-we-are/public-disclosures/2026/20261125-board-response-to-the-consumer-advocates-letter-urging-postponement-of-upcoming-bra.pdf?ref=aixenergy.io).
2. PJM Interconnection, L.L.C., 195 FERC ¶ 61,211 (2026); Southwest Power Pool, Inc., 195 FERC ¶ 61,213 (2026); Midcontinent Independent System Operator, Inc., 195 FERC ¶ 61,212 (2026); California Independent System Operator Corp., 195 FERC ¶ 61,214 (2026); ISO New England Inc., 195 FERC ¶ 61,215 (2026); New York Independent System Operator, Inc., 195 FERC ¶ 61,216 (2026). On the informational report on resource adequacy, see ISO New England, "Large Loads Integration Key Project," accessed November 27, 2026, [https://www.iso-ne.com/committees/key-projects/large-loads-integration-key-project](https://www.iso-ne.com/committees/key-projects/large-loads-integration-key-project?ref=aixenergy.io).
3. ISO New England Inc. et al., "Revisions Related to the Integration of Large Loads to the Transmission System," transmittal letter, FERC Docket No. ER27-484-000, November 13, 2026, 13-14, 84-85, [https://elibrary.ferc.gov/eLibrary/filelist?accession\_number=20261113-5007](https://elibrary.ferc.gov/eLibrary/filelist?accession%5Fnumber=20261113-5007&ref=aixenergy.io).
4. ISO New England, "ISO-NE Files Proposal with FERC to Address 'Large Loads,'" ISO Newswire, November 13, 2026, [https://isonewswire.com/2026/11/13/iso-ne-files-proposal-with-ferc-to-address-large-loads/](https://isonewswire.com/2026/11/13/iso-ne-files-proposal-with-ferc-to-address-large-loads/?ref=aixenergy.io).
5. Southwest Power Pool, Inc., "Submission of Tariff Revisions to Add the Price Adaptive Load Service," transmittal letter, FERC Docket No. ER27-578-000, November 19, 2026, 3, 30-31, 35, [https://elibrary.ferc.gov/eLibrary/filelist?accession\_number=20261119-5243](https://elibrary.ferc.gov/eLibrary/filelist?accession%5Fnumber=20261119-5243&ref=aixenergy.io).
6. Southwest Power Pool, Inc., "Submission of Tariff Revisions to Establish Load Safe Harbor Limit for Delivery Point Costs," transmittal letter, FERC Docket No. ER27-577-000, November 19, 2026, 10, [https://elibrary.ferc.gov/eLibrary/filelist?accession\_number=20261119-5227](https://elibrary.ferc.gov/eLibrary/filelist?accession%5Fnumber=20261119-5227&ref=aixenergy.io).
7. Midcontinent Independent System Operator, "Submitting Peak Load Forecast," Help Center article KA-01117, and "How Is Planning Reserve Margin Requirement (PRMR) Calculated," Help Center article KA-01065, accessed November 27, 2026, [https://help.misoenergy.org/knowledgebase/article/KA-01117/en-us](https://help.misoenergy.org/knowledgebase/article/KA-01117/en-us?ref=aixenergy.io).
8. Midcontinent Independent System Operator, Inc., "Grid Responsive Integration Transmission Service," transmittal letter, FERC Docket No. ER27-527-000, November 16, 2026, 6-8, [https://elibrary.ferc.gov/eLibrary/filelist?accession\_number=20261116-5326](https://elibrary.ferc.gov/eLibrary/filelist?accession%5Fnumber=20261116-5326&ref=aixenergy.io).
9. Coalition of Midwest Power Producers, feedback on "Non-Firm LL: Grid Responsive Integration Transmission Service (GRITS)," MISO Large Load Working Group, item LLWG-2026-5, October 8, 2026, [https://www.misoenergy.org/engage/stakeholder-feedback/2026/llwg-non-firm-ll–grid-responsive-integration-transmission-service-grits-llwg-2026-5-20261008/](https://www.misoenergy.org/engage/stakeholder-feedback/2026/llwg-non-firm-ll%E2%80%93grid-responsive-integration-transmission-service-grits-llwg-2026-5-20261008/?ref=aixenergy.io).
10. PJM Interconnection, L.L.C., 197 FERC ¶ 61,019 (2026), order accepting tariff revisions in part and rejecting tariff revisions in part, Docket No. ER26-3515-000, October 9, 2026, PP 1-3, 14, 77, [https://www.pjm.com/pjmfiles/directory/etariff/FercOrders/9207/20261009-er26-3515-000.pdf](https://www.pjm.com/pjmfiles/directory/etariff/FercOrders/9207/20261009-er26-3515-000.pdf?ref=aixenergy.io).
11. Monitoring Analytics, LLC, *2026 Quarterly State of the Market Report for PJM: January through September* (Eagleville, PA: Monitoring Analytics, November 12, 2026), sec. 1, 1-3, [https://www.monitoringanalytics.com/reports/pjm\_state\_of\_the\_market/2026/2026q3-som-pjm.pdf](https://www.monitoringanalytics.com/reports/pjm%5Fstate%5Fof%5Fthe%5Fmarket/2026/2026q3-som-pjm.pdf?ref=aixenergy.io).
12. Office of the Ohio Consumers' Counsel et al., letter to the PJM Board of Managers, "Urgent Request to Postpone the 2029/2030 Delivery Year Capacity Auction Consistent with Independent Market Monitor's Recommendation," November 18, 2026, [https://opc.maryland.gov/Portals/0/Files/Publications/Others/FIN%20PJM%20Board%20Letter%20re%20December%202026%20RPM%20auction%20%28002%29.pdf](https://opc.maryland.gov/Portals/0/Files/Publications/Others/FIN%20PJM%20Board%20Letter%20re%20December%202026%20RPM%20auction%20%28002%29.pdf?ref=aixenergy.io).
13. Ethan Howland, "PJM Urged to Delay Base Capacity Auction until Data Centers Cut from Forecast," *Utility Dive*, November 19, 2026, [https://www.utilitydive.com/news/ratepayer-advocates-pjm-market-monitor-capacity-auction/875165/](https://www.utilitydive.com/news/ratepayer-advocates-pjm-market-monitor-capacity-auction/875165/?ref=aixenergy.io).
14. New York Independent System Operator, Inc., "Large Load Integration," transmittal letter, FERC Docket No. ER27-517-000, November 16, 2026, 3, 42, 45, [https://elibrary.ferc.gov/eLibrary/filelist?accession\_number=20261116-5282](https://elibrary.ferc.gov/eLibrary/filelist?accession%5Fnumber=20261116-5282&ref=aixenergy.io).
15. California Independent System Operator Corp., "Tariff Amendment: Large Loads," transmittal letter, FERC Docket No. ER27-532-000, November 16, 2026, 6-7, [https://www.caiso.com/documents/nov-16-2026-tariff-amendment-large-loads-er27-532.pdf](https://www.caiso.com/documents/nov-16-2026-tariff-amendment-large-loads-er27-532.pdf?ref=aixenergy.io).

## Bibliography

- California Independent System Operator Corp. "Tariff Amendment: Large Loads." Transmittal letter, FERC Docket No. ER27-532-000, November 16, 2026\. [https://www.caiso.com/documents/nov-16-2026-tariff-amendment-large-loads-er27-532.pdf](https://www.caiso.com/documents/nov-16-2026-tariff-amendment-large-loads-er27-532.pdf?ref=aixenergy.io).
- Coalition of Midwest Power Producers. Feedback on "Non-Firm LL: Grid Responsive Integration Transmission Service (GRITS)." MISO Large Load Working Group, LLWG-2026-5, October 8, 2026\. [https://www.misoenergy.org/engage/stakeholder-feedback/2026/llwg-non-firm-ll--grid-responsive-integration-transmission-service-grits-llwg-2026-5-20261008/](https://www.misoenergy.org/engage/stakeholder-feedback/2026/llwg-non-firm-ll--grid-responsive-integration-transmission-service-grits-llwg-2026-5-20261008/?ref=aixenergy.io).
- Conboy, Paula. Letter to consumer advocate offices. PJM Board of Managers, November 25, 2026\. [https://www.pjm.com/-/media/DotCom/about-pjm/who-we-are/public-disclosures/2026/20261125-board-response-to-the-consumer-advocates-letter-urging-postponement-of-upcoming-bra.pdf](https://www.pjm.com/-/media/DotCom/about-pjm/who-we-are/public-disclosures/2026/20261125-board-response-to-the-consumer-advocates-letter-urging-postponement-of-upcoming-bra.pdf?ref=aixenergy.io).
- Federal Energy Regulatory Commission. *PJM Interconnection, L.L.C.*, 197 FERC ¶ 61,019 (2026). Order Accepting Tariff Revisions in Part and Rejecting Tariff Revisions in Part, Docket No. ER26-3515-000, October 9, 2026\. [https://www.pjm.com/pjmfiles/directory/etariff/FercOrders/9207/20261009-er26-3515-000.pdf](https://www.pjm.com/pjmfiles/directory/etariff/FercOrders/9207/20261009-er26-3515-000.pdf?ref=aixenergy.io).
- Howland, Ethan. "PJM Urged to Delay Base Capacity Auction until Data Centers Cut from Forecast." *Utility Dive*, November 19, 2026\. [https://www.utilitydive.com/news/ratepayer-advocates-pjm-market-monitor-capacity-auction/875165/](https://www.utilitydive.com/news/ratepayer-advocates-pjm-market-monitor-capacity-auction/875165/?ref=aixenergy.io).
- ISO New England. "ISO-NE Files Proposal with FERC to Address 'Large Loads.'" ISO Newswire, November 13, 2026\. [https://isonewswire.com/2026/11/13/iso-ne-files-proposal-with-ferc-to-address-large-loads/](https://isonewswire.com/2026/11/13/iso-ne-files-proposal-with-ferc-to-address-large-loads/?ref=aixenergy.io).
- ISO New England. "Large Loads Integration Key Project." Accessed November 27, 2026\. [https://www.iso-ne.com/committees/key-projects/large-loads-integration-key-project](https://www.iso-ne.com/committees/key-projects/large-loads-integration-key-project?ref=aixenergy.io).
- ISO New England Inc. et al. "Revisions Related to the Integration of Large Loads to the Transmission System." Transmittal letter, FERC Docket No. ER27-484-000, November 13, 2026\. [https://elibrary.ferc.gov/eLibrary/filelist?accession\_number=20261113-5007](https://elibrary.ferc.gov/eLibrary/filelist?accession%5Fnumber=20261113-5007&ref=aixenergy.io).
- Midcontinent Independent System Operator. "How Is Planning Reserve Margin Requirement (PRMR) Calculated." Help Center article KA-01065\. Accessed November 27, 2026\. [https://help.misoenergy.org/knowledgebase/article/KA-01065/en-us](https://help.misoenergy.org/knowledgebase/article/KA-01065/en-us?ref=aixenergy.io).
- Midcontinent Independent System Operator, Inc. "Grid Responsive Integration Transmission Service." Transmittal letter, FERC Docket No. ER27-527-000, November 16, 2026\. [https://elibrary.ferc.gov/eLibrary/filelist?accession\_number=20261116-5326](https://elibrary.ferc.gov/eLibrary/filelist?accession%5Fnumber=20261116-5326&ref=aixenergy.io).
- Monitoring Analytics, LLC. *2026 Quarterly State of the Market Report for PJM: January through September*. Eagleville, PA: Monitoring Analytics, November 12, 2026\. [https://www.monitoringanalytics.com/reports/pjm\_state\_of\_the\_market/2026/2026q3-som-pjm.pdf](https://www.monitoringanalytics.com/reports/pjm%5Fstate%5Fof%5Fthe%5Fmarket/2026/2026q3-som-pjm.pdf?ref=aixenergy.io).
- New York Independent System Operator, Inc. "Large Load Integration." Transmittal letter, FERC Docket No. ER27-517-000, November 16, 2026\. [https://elibrary.ferc.gov/eLibrary/filelist?accession\_number=20261116-5282](https://elibrary.ferc.gov/eLibrary/filelist?accession%5Fnumber=20261116-5282&ref=aixenergy.io).
- Office of the Ohio Consumers' Counsel et al. "Urgent Request to Postpone the 2029/2030 Delivery Year Capacity Auction Consistent with Independent Market Monitor's Recommendation." Letter to the PJM Board of Managers, November 18, 2026\. [https://opc.maryland.gov/Portals/0/Files/Publications/Others/FIN%20PJM%20Board%20Letter%20re%20December%202026%20RPM%20auction%20%28002%29.pdf](https://opc.maryland.gov/Portals/0/Files/Publications/Others/FIN%20PJM%20Board%20Letter%20re%20December%202026%20RPM%20auction%20%28002%29.pdf?ref=aixenergy.io).
- Southwest Power Pool, Inc. "Submission of Tariff Revisions to Add the Price Adaptive Load Service." Transmittal letter, FERC Docket No. ER27-578-000, November 19, 2026\. [https://elibrary.ferc.gov/eLibrary/filelist?accession\_number=20261119-5243](https://elibrary.ferc.gov/eLibrary/filelist?accession%5Fnumber=20261119-5243&ref=aixenergy.io).
- Southwest Power Pool, Inc. "Submission of Tariff Revisions to Establish Load Safe Harbor Limit for Delivery Point Costs." Transmittal letter, FERC Docket No. ER27-577-000, November 19, 2026\. [https://elibrary.ferc.gov/eLibrary/filelist?accession\_number=20261119-5227](https://elibrary.ferc.gov/eLibrary/filelist?accession%5Fnumber=20261119-5227&ref=aixenergy.io).