- Large-load queue, gross 1,136.8 GW
- Expected to be built (ELL-2.2.0) 284.2 GW
- Phantom or blocked share 75.0%
- Top-15 hyperscaler pipeline 306.6 GW
- Hyperscaler capex disclosed $2,989bn
- Verified land deeds $1,943.6m
- Utility grid-upgrade exposure $39.16bn
- Load stacked at top-25 substations 303.7 GW
- Local pushback flashpoints 112
- Nuclear and SMR contracted 38.53 GW
- Avg wholesale price, AI hub zones $51.24 $/MWh
- First release. Week-over-week changes start with the next release
- Large-load queue, gross1,136.8GWFirst releaseQueue snapshot change in Table 1: +4,425 MW (+0.39% WoW)
- Expected to be built (ELL-2.2.0)284.2GWFirst release
- Phantom or blocked share75.0%First release
- Top-15 hyperscaler pipeline306.6GWFirst release
- Hyperscaler capex disclosed$2,989bnFirst release
- Verified land deeds$1,943.6mFirst release
- Utility grid-upgrade exposure$39.16bnFirst release
- Load stacked at top-25 substations303.7GWFirst release
- Local pushback flashpoints112First release
- Nuclear and SMR contracted38.53GWFirst release
- Avg wholesale price, AI hub zones$51.24$/MWhFirst release
This is the first release in the archive, so there are no week-over-week changes yet. From next week, each figure shows its change from the previous release. Select a figure to go to its table.
AIxEnergy Weekly Media Benchmark, 2026-W46
Nine worksheets on the electricity demand of data centers and AI: queue volumes, who is building, land and capital deals, costs for ratepayers, connection waits, local opposition, nuclear and geothermal supply, and wholesale prices. Free to download; no sign-in needed.
The ZIP holds the workbook, a CSV and a JSON file for every worksheet, a data dictionary, a methodology note and checksums.
Executive brief and quotable leads
An index of the eight data tables in this release, giving each table's headline figure and a one-sentence lead written to be quoted. Start here.
Notes. Each lead summarizes the table it points to; check the table itself before publishing a figure.
Preview the first 6 of 8 rows (5 columns)
| Worksheet Tab | Standardized Weekly Table | Primary Supabase Source Tables | Headline Benchmark Metric | Ready-to-Print Journalist Soundbite |
|---|---|---|---|---|
| 01_Weekly_AI_Power_Rig_Count | 1. The Weekly 'AI Power Rig Count' | mart.weekly_rig_count_snapshots, core.large_load_request | 1,136.8 GW Gross / 284.2 GW Realized | U.S. & North American grid operators tracked 1,136.8 GW of active large-load AI & data center requests across 4,351 queue positions this week (+4,425 MW WoW), though AIxEnergy's ELL-2.2.0 realization model projects only 284.2 GW (25.0%) will ultimately energize (19.5%–32.5% across ISOs)—leaving 75.0% (852.6 GW) as phantom, speculative, or policy/pushback-blocked requests. |
| 02_Hyperscaler_Power_Scoreboard | 2. The Hyperscaler Power Scoreboard | canonical.canonical_projects, capital.capital_metrics | 306.6 GW / $2,989.1B Disclosed CapEx | The top 15 hyperscalers and AI infrastructure developers now control 306.6 GW of active data center power pipeline backed by $2,989.1B in disclosed capital commitments ($9.75M/MW avg intensity) and 15.28 GW of contracted nuclear & firm geothermal baseload. |
| 03_Weekly_Megadeal_Deed_Log | 3. The Weekly Megadeal & Land Deed Log | deal.v_verified_land_deeds, capital.capital_events | $1,943.6M Verified Deeds ($187,797/acre) | Verified county recorder deeds tracked $1,943.6M in hyperscaler land acquisitions across 10,350 acres (averaging $187,797/acre), led by Amazon's $650M Susquehanna nuclear campus deed and Microsoft's $215M Loudoun assemblage. |
| 04_Ratepayer_Cost_Exposure | 4. Ratepayer Cost Exposure & Tariff Watch | mart.utility_summary, core.regulatory_filing | $39.16B Transmission Upgrade Exposure | Across the top 22 U.S. electric utilities facing 716.1 GW of large-load requests, regulators are tracking $39.16B in required transmission and substation upgrades—prompting mandatory 80%–85% minimum demand ratchets in Ohio, Virginia, Indiana, Georgia, and Texas. |
| 05_Time_To_Power_Waitlist | 5. 'Time-to-Power' Substation Waitlist Index | mart.large_load_master, core.substation_upgrade | 303.7 GW across Top 25 Hubs (34–52m Wait) | The top 25 most congested U.S. substation corridors hold 303.7 GW of stacked data center load requests, facing an average queue dwell time of 27.2 months and EHV transformer delivery lead times of 34–52 months (pushing new energizations to 2028–2030). |
| 06_Moratoria_And_Subsidies | 6. Moratorium, Pushback & Tax Subsidy Ledger | core.local_public_pushback, deal.v_verified_pilot_incentives | 112 Pushback Hubs vs. 8 Statutory PILOTs | AIxEnergy tracks 112 active municipal pushback & moratorium flashpoints alongside 55 restrictive local zoning/grid policy regimes—even as pro-growth jurisdictions approved $50.4B in statutory PILOT tax-abatement megadeals tied to strict job and CapEx clawbacks. |
Worksheet 00_Executive_Brief_And_Quotes in the 2026-W46 workbook.
The weekly AI power rig count
Large-load (data center and AI) interconnection requests in grid queues, by grid operator: how many requests, how much capacity they ask for, the change since the previous weekly queue snapshot, and how much of it AIxEnergy's ELL-2.2.0 model expects to be built.
- Gross Active Queue1,136.83 GW4,351 projects
- Weekly Net Change+4,425 MW+0.39% WoW
- Realization-Adjusted284.22 GW25.0% P-Eventual
- Phantom/Speculative Share75.0%852.6 GW
Quotable leadU.S. & North American grid operators tracked 1,136.8 GW of active large-load AI & data center requests across 4,351 queue positions this week (+4,425 MW WoW), though AIxEnergy's ELL-2.2.0 realization model projects only 284.2 GW (25.0%) will ultimately energize (19.5%–32.5% across ISOs)—leaving 75.0% (852.6 GW) as phantom, speculative, or policy/pushback-blocked requests.
Notes. Gross figures are requested capacity. Realization-adjusted figures and the phantom share are model estimates, not grid-operator forecasts. The last row is the total.
Preview the first 6 of 10 rows (12 columns)
| ISO / Grid Operator | Active Queue Positions | Gross Requested (GW) | WoW Net Change (MW) | WoW Change (%) | Realization-Adjusted (GW) | Mean P(Eventual) (%) | Phantom Queue Share (%) | Committed / Construction (GW) | Energized Operating (GW) | 30-Day Withdrawn (MW) | Median Queue Dwell (Mos) |
|---|---|---|---|---|---|---|---|---|---|---|---|
| ERCOT | 798 | 269.9 | 1480 | 0.55 | 57.22 | 21.2 | 78.8 | 38.4 | 24.7 | 685 | 34 |
| PJM | 1341 | 265.58 | 920 | 0.35 | 72.77 | 27.4 | 72.6 | 52.1 | 45.39 | 430.9 | 46 |
| NYISO | 861 | 169.91 | 310 | 0.18 | 33.13 | 19.5 | 80.5 | 18.45 | 5.62 | 345 | 42 |
| MISO | 261 | 129.11 | 640 | 0.5 | 34.6 | 26.8 | 73.2 | 24.8 | 11.18 | 280 | 38 |
| SERC | 416 | 98.16 | 420 | 0.43 | 31.9 | 32.5 | 67.5 | 22.6 | 15.59 | 195 | 32 |
| WECC | 217 | 73.28 | 290 | 0.4 | 20.37 | 27.8 | 72.2 | 14.5 | 9.96 | 179.2 | 40 |
Worksheet 01_Weekly_AI_Power_Rig_Count in the 2026-W46 workbook.
The hyperscaler power scoreboard
The 15 largest sponsors of data center campuses in the AIxEnergy project database, ranked by total pipeline load, with construction status, disclosed and committed capital spending, and contracted nuclear and geothermal supply.
- Top 15 Total Pipeline306.59 GW1,665 campuses
- Under Construction124.72 GW Active Build
- Disclosed CapEx$2,989.1B$1,724.5B Committed
- Contracted Nuclear/Geo15.28 GW Firm Clean
Quotable leadThe top 15 hyperscalers and AI infrastructure developers now control 306.6 GW of active data center power pipeline backed by $2,989.1B in disclosed capital commitments ($9.75M/MW avg intensity) and 15.28 GW of contracted nuclear & firm geothermal baseload.
Notes. Campuses are attributed to sponsors by matching developer, operator and customer names. GPU capacity is an estimate. The last row is the total.
Preview the first 6 of 16 rows (11 columns)
| Rank | Hyperscaler / Sponsor Organization | Tracked Campuses | Total Pipeline Load (GW) | Under Construction / Committed (GW) | Energized Operating (GW) | Disclosed CapEx ($B) | Committed CapEx ($B) | CapEx Intensity ($M/MW) | Contracted Nuclear & Geo (MW) | Est. B200-Eqv GPU Capacity |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Microsoft | 137 | 52.42 | 20.76 | 4.31 | 568.77 | 223.16 | 10.85 | 2905 | 224,800 |
| 2 | Oracle / OpenAI (Stargate) | 36 | 34.03 | 23.25 | 0.26 | 425.4 | 239.82 | 12.5 | 1650 | 165,000 |
| 3 | Amazon / AWS | 276 | 33.1 | 16.48 | 6 | 370.76 | 211.33 | 11.2 | 2920 | 294,500 |
| 4 | Tract (Master Planned Parks) | 16 | 29.42 | 4.05 | 4.05 | 63.25 | 22.86 | 2.15 | 0 | 15,000 |
| 5 | Meta Platforms | 78 | 27.01 | 18.15 | 6.16 | 280.87 | 212.69 | 10.4 | 2450 | 142,000 |
| 6 | Alphabet / Google | 95 | 20.68 | 12.35 | 3.31 | 220.27 | 142.53 | 10.65 | 1865 | 188,400 |
Worksheet 02_Hyperscaler_Power_Scoreboard in the 2026-W46 workbook.
Megadeal and county land-deed log
Verified county land deeds for data center sites, with buyer, seller, county, amount, acreage and price per acre, alongside capital-spending announcements of $1 billion or more. Each row carries its filing or source citation.
- Verified Land Deeds$1,943.6M10 deeds
- Total Conveyed Acreage10,349.5 Acres
- Weighted Avg Land Price$187,797 / Acre
- Megadeal CapEx Filings12 Transactions ≥ $1.0B
Quotable leadVerified county recorder deeds tracked $1,943.6M in hyperscaler land acquisitions across 10,350 acres (averaging $187,797/acre), led by Amazon's $650M Susquehanna nuclear campus deed and Microsoft's $215M Loudoun assemblage.
Notes. Deed amounts are as recorded; megadeal amounts are as announced by the sponsor.
Preview the first 6 of 22 rows (11 columns)
| Recording / Filing Date | Transaction Type | Project / Campus Name | Buyer / Sponsor Entity | Seller / Counterparty | County & State | Verified Amount ($M) | Conveyed Acreage | Price per Acre ($/Ac) | Associated Campus MW | Statutory Instrument / Filing Citation |
|---|---|---|---|---|---|---|---|---|---|---|
| 2026-11-09 | LAND DEED RECORDING | AWS Madison County Mega Data Center Campus | Amazon Data Services, Inc. | Madison County Economic Dev. Authority | Madison County, MS | 126 | 920 | 136,957 | 1300 | INST-2026-44109 (BK-4215/PG-0118) |
| 2026-11-04 | LAND DEED RECORDING | Stargate Abilene (Crusoe / Oracle / OpenAI Campus) | Crusoe / Oracle Stargate JV LLC | Lancium Clean Campus LLC | Taylor County, TX | 184 | 1100 | 167,273 | 1400 | DOC-2026-110482 (OPR-2026/PG-5501) |
| 2026-10-28 | LAND DEED RECORDING | Google Buckeye / West Valley AI Campus | Google LLC (Sidewinder Acquisition LLC) | Buckeye Valley Holdings LLC | Maricopa County, AZ | 178 | 740 | 240,541 | 1000 | MCR-2026-0841920 (BK-2026/PG-8419) |
| 2026-10-22 | LAND DEED RECORDING | Microsoft Mount Pleasant AI Supercomputing Campus | Microsoft Corporation | Village of Mount Pleasant CDA | Racine County, WI | 99.7 | 1030 | 96,796 | 1200 | DOC-2694812 (VOL-4810/PG-305) |
| 2026-10-14 | LAND DEED RECORDING | AWS New Carlisle Mega Data Center Campus | Amazon Data Services, Inc. | New Carlisle Industrial Corridor LLC | St. Joseph County, IN | 134 | 880 | 152,273 | 2200 | INST-2026-29410 (BK-2026/PG-0912) |
| 2026-10-04 | LAND DEED RECORDING | Microsoft Compass / Dulles South Campus | Microsoft Corporation (SI Va LLC) | Dulles South Land Holdings LLC | Loudoun County, VA | 215 | 342 | 628,655 | 600 | INST-20261004-0051820 (BK-4120/PG-0881) |
Worksheet 03_Weekly_Megadeal_Deed_Log in the 2026-W46 workbook.
Ratepayer cost exposure and utility tariff watch
The 22 utilities with the most large-load capacity requested, how much of it is expected to materialize (and within 24 and 60 months), an estimate of the grid-upgrade cost involved, and the docket or tariff that decides who pays.
- Top 22 Utilities Queue716.15 GW Gross Requested
- Realization-Expected Load171.98 GW Expected
- Substation/Tx Exposure$39.16B Tracked Upgrades
- Dominant Tariff Rule80–85% Min Demand / 12–20 Yr Term
Quotable leadAcross the top 22 U.S. electric utilities facing 716.1 GW of large-load requests, regulators are tracking $39.16B in required transmission and substation upgrades—prompting mandatory 80%–85% minimum demand ratchets in Ohio, Virginia, Indiana, Georgia, and Texas.
Notes. Expected-load columns come from the ELL-2.2.0 model. Upgrade-cost estimates and the docket and tariff descriptions are AIxEnergy analyst assignments for each utility, not totals taken from utility filings. The last row is the total.
Preview the first 6 of 23 rows (10 columns)
| ISO / RTO | Electric Utility / Transmission Owner | Active Load Requests | Gross Queued Load (GW) | Realization-Expected Load (GW) | 24-Month Expected (GW) | 60-Month Expected (GW) | Est. Grid Upgrade Exposure ($M) | Key Regulatory Docket | Ratepayer Protection & Tariff Mechanism |
|---|---|---|---|---|---|---|---|---|---|
| ERCOT | Oncor Electric Delivery | 434 | 137.97 | 29.25 | 15.79 | 27.49 | 3420 | PUCT 57152 / ERCOT SB 6 | 100% Substation CIAC Deposit + ERCOT Study |
| PJM | Dominion Energy Virginia | 509 | 68.75 | 18.84 | 10.17 | 17.71 | 4850 | VA SCC PUR-2024-00144 | 14-Yr Contract / 85% T&D Demand Ratchet |
| NYISO | National Grid (Upstate NY) | 319 | 63.16 | 12.32 | 6.65 | 11.58 | 1120 | NYPSC Case 24-E-0364 | Upfront 345 kV Transmission Security Deposit |
| NYISO | New York Power Authority (NYPA) | 131 | 49.25 | 9.6 | 5.19 | 9.03 | 620 | NYPA Large Load Allocation | Statutory Industrial Hydro Allocation Cap |
| MISO | Entergy (Louisiana / Mississippi / Texas) | 23 | 42.82 | 11.48 | 6.2 | 10.79 | 2250 | LA PSC U-37425 / MS PSC | Dedicated CCGT Generation & 500/345 kV Rider |
| PJM | Commonwealth Edison (ComEd) | 188 | 40.66 | 11.14 | 6.02 | 10.47 | 1680 | ICC Large Load Rider TS | 10-Yr Minimum Capacity Commitment & CIAC |
Worksheet 04_Ratepayer_Cost_Exposure in the 2026-W46 workbook.
Time-to-power: substation bottlenecks
The 25 substation corridors with the most data center load stacked in the queue, with voltage, number of requests, gross and realization-adjusted load, and the expected wait to connect.
- Top 25 Bottleneck Hubs303.74 GW Stacked Load
- Realization-Expected Load71.59 GW Realized
- Mean Queue Dwell Time27.2 Months
- EHV Upgrade Lead Time34–52 Months2028–2030 COD
Quotable leadThe top 25 most congested U.S. substation corridors hold 303.7 GW of stacked data center load requests, facing an average queue dwell time of 27.2 months and EHV transformer delivery lead times of 34–52 months (pushing new energizations to 2028–2030).
Notes. Queue dwell, equipment lead times, target energization windows and the bottleneck descriptions are AIxEnergy engineering estimates for each corridor.
Preview the first 6 of 25 rows (12 columns)
| Rank | ISO / RTO | Host Utility | Substation / POI Corridor | Voltage (kV) | Stacked Requests | Gross Queued Load (GW) | Realization-Adjusted Load (GW) | Avg Queue Dwell (Mos) | Upgrade Lead Time (Mos) | Target Energization Window | Primary Physical Grid Bottleneck |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | ERCOT | Texas-New Mexico Power Company | Solstice / Reeves-Pecos 345kV Permian Hub | 345 | 28 | 48.23 | 10.22 | 24.5 | 40 | Q1 2029 | Permian 345/765kV Dynamic Reactive & Series Compensation |
| 2 | MISO | Entergy Louisiana | Richland 345kV Hub | 500 | 6 | 30 | 8.04 | 19.8 | 36 | Q4 2028 | 500/230kV Autotransformer Bank & Dedicated CCGT Tie |
| 3 | ERCOT | Oncor Electric Delivery | Sweetwater / Nolan County 345kV CREZ Hub | 345 | 28 | 26.4 | 5.6 | 26.2 | 38 | Q2 2029 | West Texas CREZ 345kV Thermal Export & Short-Circuit Limit |
| 4 | PJM | NOVEC (Northern Virginia Electric Cooperative) | Loudoun 345kV Hub | 500 | 200 | 18.28 | 5.01 | 38.6 | 52 | Q4 2030 | 500/230kV GIS Breaker Bay & Golden-Mars 500kV Loop |
| 5 | PJM | AEP Ohio | Pike 345kV Hub | 345 | 2 | 16 | 4.38 | 27.8 | 42 | Q3 2029 | Piketon 345kV Portsmouth-Don Marquis Loop Thermal Limit |
| 6 | ERCOT | Bluebonnet Electric Cooperative (LCRA) | Caldwell 345kV Hub | 345 | 3 | 12 | 2.54 | 22.4 | 38 | Q2 2029 | LCRA-Bluebonnet 345kV Lockhart Switching Station |
Worksheet 05_Time_To_Power_Waitlist in the 2026-W46 workbook.
Moratoria, local pushback and tax subsidies
Local moratoria and public-pushback actions against data centers, set against statutory PILOT tax-abatement deals and the minimum capital spending and jobs they require.
- Civic Pushback Flashpoints112 Tracked Jurisdictions
- Restrictive Policy Regimes55 Local Ordinances/Rules
- Verified PILOT Megadeals8 Statutory Awards
- Clawback-Backed CapEx$50.4B Committed
Quotable leadAIxEnergy tracks 112 active municipal pushback & moratorium flashpoints alongside 55 restrictive local zoning/grid policy regimes—even as pro-growth jurisdictions approved $50.4B in statutory PILOT tax-abatement megadeals tied to strict job and CapEx clawbacks.
Notes. The headline counts of pushback flashpoints and restrictive policy regimes cover AIxEnergy's full tracker; the table lists a selection of them.
Preview the first 6 of 23 rows (10 columns)
| Ledger Category | Jurisdiction & State | Action / Approval Date | Target Campus / Project | Developer / Sponsor | Action Type / Abatement Terms | Legal Status / Ordinance Citation | Clawback Min CapEx ($B) | Min Jobs Requirement | Summary & Policy Impact |
|---|---|---|---|---|---|---|---|---|---|
| CIVIC PUSHBACK / MORATORIUM | Washtenaw County, Michigan | 2026-09-24 | Saline Township data center / Stargate-related proposal | Related project entities | Public hearing | Township planning commission tabled the rezoning request for 60 days to solicit additional grid studies | — | — | Residents filled the township hall to oppose a proposed 120 MW computing center, challenging rezoning from light industrial and highlighting DTE electric substation expansion and noise near residential subdivisions. |
| CIVIC PUSHBACK / MORATORIUM | Travis County, Texas | 2026-09-21 | Multiple Proposed Campuses | Multiple Developers | Rally or protest | Governor issued directive halting all new TCEQ data center permits hours after petition delivery | — | — | A coalition of ratepayer advocacy and conservation groups delivered thousands of petition signatures to the Texas Capitol highlighting ERCOT grid strain and Hill Country groundwater depletion from rapid data center buildouts, preceding Governor Abbott's directive halting TCEQ permits. |
| CIVIC PUSHBACK / MORATORIUM | Montgomery County, Maryland | 2026-08-10 | New Montgomery County data centers | Multiple / prospective | Government response | Building-permit pause enacted | — | — | Expedited Bill 19-26 was signed August 10 after an 11–0 council vote, establishing a moratorium on data-center building permits in Montgomery County, Maryland. |
| CIVIC PUSHBACK / MORATORIUM | Lyon County, Kansas | 2026-11-03 | Emporia data-center proposal | Project applicant | Ballot referendum | Both 10-year municipal bans approved by voters on Nov 3, 2026 | — | — | On November 3, 2026, voters in Emporia (~60% yes) and El Dorado (~71% yes) approved citizen-petitioned ballot initiatives enacting 10-year bans on high-impact data centers exceeding 10 MW of electric load or 100,000 gallons of daily water consumption, as well as large battery storage systems. |
| CIVIC PUSHBACK / MORATORIUM | Middlesex County, New Jersey | 2026-09-23 | Princeton Nurseries Data Center | Princeton Digital Infra | Legal challenge | Lawsuit filed; expedited injunction hearing set for November 2026 | — | — | Community groups filed suit in state court challenging air quality permits issued for 36 backup diesel generators at a proposed data center campus, citing PM2.5 pollution near elementary schools and noise violations under local decibel limits. |
| CIVIC PUSHBACK / MORATORIUM | Prince William County, Virginia | 2026-09-22 | Prince William Digital Gateway | QTS and Compass Datacenters | Government response | By-right status abolished; SUP mandatory; overlay reduced from ~9,700 to 3,641 acres | — | — | Following months of grassroots organizing, yard sign campaigns, and extensive public testimony, coalition leaders secured an 8-0 Board of Supervisors vote stripping by-right development privileges from data centers and shrinking the county overlay district by over 6,000 acres. |
Worksheet 06_Moratoria_And_Subsidies in the 2026-W46 workbook.
Nuclear, SMR and geothermal deal tracker
Contracts and announced pairings between data center operators and nuclear plants, small modular reactors and enhanced-geothermal projects: plant, offtaker, technology, contracted megawatts, regulatory stage, target operating date and a state nuclear-policy score.
- Nuclear & SMR Contracted38.53 GW37 plants
- Geothermal (EGS) Deals1,444 MW14 pairings
- Total Clean Firm Baseload39.97 GW
- State Nuclear Regimes51 States/DC ScoredTiers 1–5
Quotable leadHyperscalers have now contracted 38.53 GW across 37 nuclear & SMR plants plus 1,444 MW across 14 next-generation geothermal (EGS) pairings (39.97 GW total firm 24/7 clean baseload).
Notes. Contracted MW includes planned and announced deals, not only operating supply. The last row is the total.
Preview the first 6 of 52 rows (16 columns)
| Clean Firm Pillar | Deal Category | Plant / Resource Name | Generator / Developer Owner | Data Center Offtaker | Paired Data Center Campus | State / Province | ISO / Grid Region | Reactor / Resource Technology | Delivery Mode (BTM / FTM) | Contracted / Planned MW | Operating Plant MW | Stage / Regulatory Status | Target COD | State Nuclear Policy Tier | State Policy Score |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| NUCLEAR / SMR | Advanced SMR — Master Power Agreement | Oklo × Switch 12 GW Aurora Fast Reactor Master Power Agreement Fleet | Oklo Inc. | Switch, Inc. | Switch Citadel Campus (Tahoe-Reno), Las Vegas Core Campus, Atlanta Keep & Texas Rock | NV | NEVP | Liquid Metal-Cooled Fast Reactor (Oklo Aurora 15–75 MWe Modular Fast Reactors) | Behind-the-Meter (BTM) Co-Located & Grid-Connected Corporate PPAs | 12,000 | 0 | Announced / Master Framework Agreement (Site-specific PPAs in development) | Late 2020s–2044 Phased Rollout | Tier 3: Coal-to-Nuclear / SMR Enabling | 68 |
| NUCLEAR / SMR | Large-Scale Gen III+ Nuclear — Co-Located AI Megacampus | Project Matador Nuclear Station (Fermi America HyperGrid 4 × AP1000) | Fermi Nuclear LLC (Fermi America / Texas Tech University System) | Fermi HyperGrid AI Campus & TensorWave Phase 1 (Amarillo / Carson County TX) | Fermi HyperGrid Campus & Fermi Project Matador – TensorWave Phase 1 | TX | SWPP / ERCOT | Pressurized Water Reactor (4 × Westinghouse AP1000 Gen III+) | Behind-the-Meter (BTM) Co-Located at Pantex / Texas Tech Research Park | 4468 | 0 | Planned / NRC Combined License (COL) Application Accepted for Review (2025) | 2032 (Unit 1 target); mid-2030s (4-unit buildout) | Tier 1: Flagship Accelerator | 96 |
| NUCLEAR / SMR | Operating Nuclear Fleet — Co-Located / FTM PPA | Susquehanna Steam Electric Station Units 1 & 2 | Talen Energy Corporation (Susquehanna Nuclear, LLC) | Amazon Web Services (AWS) | AWS Salem Township AI Data Center Campus (Cumulus Site at Susquehanna) | PA | PJM | Boiling Water Reactor (2 × GE BWR-4 / Mark II) | Co-Located BTM transitioning to Front-of-the-Meter (FTM) via PPL Electric (Spring 2026) | 1920 | 2532 | Operational (Units 1 & 2 online 1983/1985; FTM Reconfiguration 2026) | Operational (Full 1,920 MW ramp by 2032) | Tier 2: Pro-Nuclear Fleet & ZEC / Restart | 88 |
| NUCLEAR / SMR | Advanced SMR — Shipyard-Fabricated BTM AI Campus | Port of Victoria Modular Nuclear Power Plant (Blue Energy × Crusoe) | Blue Energy Inc. | Crusoe Energy Systems LLC | Crusoe Port of Victoria AI Data Center Campus (Victoria County, TX) | TX | ERCOT | Small Modular Reactor (Shipyard-Manufactured Light-Water / BWRX-300 Class Modular Plant) | Behind-the-Meter (BTM) Co-Located (Gas-to-Nuclear Phased Transition) | 1500 | 0 | Announced / Site Leased at Port of Victoria (NRC Pre-Application) | 2031 (Nuclear Phase; Gas Bridge 2028) | Tier 1: Flagship Accelerator | 96 |
| NUCLEAR / SMR | Operating Nuclear Fleet — Long-Term PPA + Uprate | Perry Nuclear Power Plant Unit 1 | Vistra Corp. (Energy Harbor Nuclear Corp.) | Meta Platforms, Inc. | Meta New Albany & Prometheus Supercluster AI Data Center Campuses (Central Ohio) | OH | PJM | Boiling Water Reactor (GE BWR-6 / Mark III) | Grid-Connected (PJM ATSI Zone) | 1268 | 1311.6 | Operational (Online 1987; Uprate in engineering for early 2030s) | Operational (Meta PPA starts late 2026; uprates through 2034) | Tier 2: Pro-Nuclear Fleet & ZEC / Restart | 84 |
| NUCLEAR / SMR | Operating Nuclear Fleet — Co-Located / Long-Term PPA | Comanche Peak Nuclear Power Plant Units 1 & 2 | Vistra Corp. (Luminant Generation Company LLC) | Amazon Web Services (AWS) | Comanche Peak Nuclear Data Center ('Project Spectrum' — Hood/Somervell TX) | TX | ERCOT | Pressurized Water Reactor (2 × Westinghouse 4-Loop PWR) | Grid-Connected ERCOT + Co-Located Somervell County Site ('Project Spectrum') | 1200 | 2430 | Operational (Units 1 & 2 online 1990/1993; NRC licensed through 2050/2053) | Operational (1,200 MW PPA delivery ramps Q4 2027 – Q4 2032) | Tier 1: Flagship Accelerator | 96 |
Worksheet 07_Nuclear_Geothermal_Deals in the 2026-W46 workbook.
Wholesale power prices in AI hub zones
Average 2026 day-ahead, real-time and load-weighted wholesale power prices in 24 pricing zones with heavy data center development, the change from 2025, the technology that most often sets the marginal price, and its carbon intensity.
- Tracked AI Hub Zones24 Pricing Zones9 ISOs
- 2026 Load-Weighted LMP$51.24 / MWh
- Mean YoY Price Escalation+8.7% YoY2026 vs. 2025
- Dominant Marginal FuelNatural Gas CC/CT60.2% hours
Quotable leadAcross the 24 primary North American AI data center pricing zones (spanning all 9 ISOs), load-weighted wholesale electricity prices averaged $51.24/MWh in 2026 (+8.7% YoY, led by PJM Dominion at +14.8% and ERCOT West at +12.4%), with natural gas and dual-fuel units setting the marginal price in 60.2% of hours.
Notes. Marginal CO₂ intensities are zone-level reference values. Where a zone has no 2025 annual figure, the 2025 price is back-estimated.
Preview the first 6 of 24 rows (12 columns)
| ISO / RTO | Zone ID | Pricing Zone / AI Hub Name | 2026 Avg Day-Ahead LMP ($/MWh) | 2026 Avg Real-Time LMP ($/MWh) | 2026 Load-Weighted LMP ($/MWh) | 2025 Load-Weighted LMP ($/MWh) | YoY LMP Change (%) | Total Zone Cost Exposure ($B) | Dominant Marginal Technology | Marginal Tech Share (%) | Marginal CO2 Intensity (kg/MWh) |
|---|---|---|---|---|---|---|---|---|---|---|---|
| PJM | PJM_DOM | Dominion Virginia (Data Center Alley) | 68.56 | 70.4 | 71.4 | 62.2 | 14.8 | 9.45 | NG_CC | 64.2 | 418 |
| MISO | MISO_LRZ9 | MISO LRZ 9 (Louisiana & East Texas) | 56.33 | 56.67 | 58.23 | 53.32 | 9.2 | 8.51 | NG_CC | 74.8 | 402 |
| ERCOT | ERCOT_NORTH | ERCOT North Hub (DFW / Abilene) | 49.38 | 50.71 | 52.8 | 47.4 | 11.4 | 7.84 | NG_CC | 68.5 | 394 |
| PJM | PJM_AEP | AEP Ohio / Appalachian Zone | 51.2 | 52.85 | 54.1 | 47.62 | 13.6 | 7.42 | COAL_NG | 61.8 | 568 |
| MISO | MISO_LRZ7 | MISO LRZ 7 (Michigan Lower Peninsula) | 54.59 | 54.97 | 56.42 | 52.48 | 7.5 | 7.25 | NG_CC | 66.4 | 472 |
| PJM | PJM_COMED | Commonwealth Edison (Northern Illinois) | 46.8 | 48.15 | 49.78 | 45.1 | 10.4 | 6.48 | NG_CC | 57.6 | 356 |
Worksheet 08_Wholesale_Price_Pulse in the 2026-W46 workbook.
Every release
Each Monday's release is added here. Files from earlier weeks stay at the same addresses and are not changed after publication, so a figure you cite can always be traced back to its file.
This is the first published release.
How to use and cite this data
- Which file should I download?
- Excel if you want the formatted tables with their headline banners; CSV for spreadsheets, Datawrapper, Flourish or code; JSON if you are building something. CSV and JSON files hold only the data rows under a single header row.
- How should I cite it?
- Name the release week, so readers can find the exact file:AIxEnergy Weekly Media Benchmark, 2026-W46 (data as of November 15, 2026). AIxEnergy. https://aixenergy.io/benchmarks/
- Which figures are estimates?
- Anything labeled realization-adjusted, expected, P(eventual) or phantom comes from the ELL-2.2.0 model and should be described as an AIxEnergy estimate. Gross queue figures are requested capacity, not demand that will appear on the grid. Each table's notes flag analyst-assigned columns.
- When is it updated?
- Every Monday morning, US Eastern time. Releases are labeled by ISO week (for example 2026-W46); the as-of date is the last day of that week. Earlier releases stay in the archive.
- Can I check a file has not been altered?
- Yes. Each workbook's SHA-256 checksum is listed above and in the archive, and the ZIP includes checksums for every file inside it.
- Questions, corrections or interviews
- Email bowens@aixenergy.io (Brandon N. Owens, Chief Executive Officer, AIxEnergy). Please include the release week and table number.
How the figures are produced
What the benchmark is
The AIxEnergy Weekly Media Benchmark is a set of standardized tables on electricity demand from data centers and AI, drawn each week from the AIxEnergy database. That database combines grid-operator and utility large-load queue records, project and capital-spending records, county land deeds, local policy and public-pushback records, nuclear and geothermal supply deals, and wholesale market prices.
Gross versus realization-adjusted load
Interconnection queues overstate what will be built: developers file in several places at once, and many requests are speculative or are stopped by cost, policy or local opposition. Gross figures report capacity as requested. Realization-adjusted figures weight each request by its estimated probability of eventually being energized under AIxEnergy's ELL-2.2.0 large-load realization model. The difference between the two is reported as the phantom or blocked share.
The ELL-2.2.0 model
ELL-2.2.0 assigns each large-load request a probability of eventual energization, and probabilities of energization within 24 and 60 months. It runs as a national model with separate versions for nine grid regions (ERCOT, PJM, MISO, SPP, CAISO, NYISO, BPA/Northwest, WECC Southwest/Mountain and SERC), each reflecting that region's queue rules, collateral and tariff requirements, local moratoria and public pushback. Its regional realization rates currently range from 19.5% to 32.5%. Its outputs are estimates, not forecasts by grid operators or utilities, and should be reported as AIxEnergy estimates.
Analyst inputs
Some columns are AIxEnergy analyst or engineering assignments rather than database records: utility grid-upgrade cost estimates and the docket and tariff descriptions in table 4; queue dwell, equipment lead times, target windows and bottleneck descriptions in table 5; and marginal carbon intensities in table 8. Each table's notes say which.
Release cadence and integrity
A new release is published each Monday morning (US Eastern time), labeled by ISO week; the as-of date is the last day of that week. Each workbook carries a SHA-256 checksum, and files from earlier weeks stay available in the archive unchanged. Week-over-week changes on this page compare a release with the previous one in the archive.