Benchmarks

Weekly data on the power demands of AI and data centers, built for reporters: nine worksheets, each free to download as Excel, CSV or JSON, with a citable archive of every release. No sign-in needed.


Share this post
2026-W46
  • Large-load queue, gross 1,136.8 GW
  • Expected to be built (ELL-2.2.0) 284.2 GW
  • Phantom or blocked share 75.0%
  • Top-15 hyperscaler pipeline 306.6 GW
  • Hyperscaler capex disclosed $2,989bn
  • Verified land deeds $1,943.6m
  • Utility grid-upgrade exposure $39.16bn
  • Load stacked at top-25 substations 303.7 GW
  • Local pushback flashpoints 112
  • Nuclear and SMR contracted 38.53 GW
  • Avg wholesale price, AI hub zones $51.24 $/MWh
  • First release. Week-over-week changes start with the next release
The week in numbers · Week 46, 2026Week of November 9, 2026 to November 15, 2026

This is the first release in the archive, so there are no week-over-week changes yet. From next week, each figure shows its change from the previous release. Select a figure to go to its table.

Latest release

AIxEnergy Weekly Media Benchmark, 2026-W46

Nine worksheets on the electricity demand of data centers and AI: queue volumes, who is building, land and capital deals, costs for ratepayers, connection waits, local opposition, nuclear and geothermal supply, and wholesale prices. Free to download; no sign-in needed.

Release
2026-W46 (Week 46, 2026)
Data as of
November 15, 2026
Model
ELL-2.2.0 load-realization model (methodology)
Contents
9 worksheets, 203 data rows
SHA-256
37c31d504053a6a0bf8f6498dcf67fa40696f4d2ff01a9aed13c46a67eb7549f

The ZIP holds the workbook, a CSV and a JSON file for every worksheet, a data dictionary, a methodology note and checksums.

In this release
No.TableHeadlineRowsQuick file
0Executive brief and quotable leadsIndex and quotable leads8CSV
1The weekly AI power rig count1,136.83 GW (4,351 projects)10CSV
2The hyperscaler power scoreboard306.59 GW (1,665 campuses)16CSV
3Megadeal and county land-deed log$1,943.6M (10 deeds)22CSV
4Ratepayer cost exposure and utility tariff watch716.15 GW Gross Requested23CSV
5Time-to-power: substation bottlenecks303.74 GW Stacked Load25CSV
6Moratoria, local pushback and tax subsidies112 Tracked Jurisdictions23CSV
7Nuclear, SMR and geothermal deal tracker38.53 GW (37 plants)52CSV
8Wholesale power prices in AI hub zones24 Pricing Zones (9 ISOs)24CSV
Overview · 8 rows

Executive brief and quotable leads

An index of the eight data tables in this release, giving each table's headline figure and a one-sentence lead written to be quoted. Start here.

Notes. Each lead summarizes the table it points to; check the table itself before publishing a figure.

Preview the first 6 of 8 rows (5 columns)
Worksheet TabStandardized Weekly TablePrimary Supabase Source TablesHeadline Benchmark MetricReady-to-Print Journalist Soundbite
01_Weekly_AI_Power_Rig_Count1. The Weekly 'AI Power Rig Count'mart.weekly_rig_count_snapshots, core.large_load_request1,136.8 GW Gross / 284.2 GW RealizedU.S. & North American grid operators tracked 1,136.8 GW of active large-load AI & data center requests across 4,351 queue positions this week (+4,425 MW WoW), though AIxEnergy's ELL-2.2.0 realization model projects only 284.2 GW (25.0%) will ultimately energize (19.5%–32.5% across ISOs)—leaving 75.0% (852.6 GW) as phantom, speculative, or policy/pushback-blocked requests.
02_Hyperscaler_Power_Scoreboard2. The Hyperscaler Power Scoreboardcanonical.canonical_projects, capital.capital_metrics306.6 GW / $2,989.1B Disclosed CapExThe top 15 hyperscalers and AI infrastructure developers now control 306.6 GW of active data center power pipeline backed by $2,989.1B in disclosed capital commitments ($9.75M/MW avg intensity) and 15.28 GW of contracted nuclear & firm geothermal baseload.
03_Weekly_Megadeal_Deed_Log3. The Weekly Megadeal & Land Deed Logdeal.v_verified_land_deeds, capital.capital_events$1,943.6M Verified Deeds ($187,797/acre)Verified county recorder deeds tracked $1,943.6M in hyperscaler land acquisitions across 10,350 acres (averaging $187,797/acre), led by Amazon's $650M Susquehanna nuclear campus deed and Microsoft's $215M Loudoun assemblage.
04_Ratepayer_Cost_Exposure4. Ratepayer Cost Exposure & Tariff Watchmart.utility_summary, core.regulatory_filing$39.16B Transmission Upgrade ExposureAcross the top 22 U.S. electric utilities facing 716.1 GW of large-load requests, regulators are tracking $39.16B in required transmission and substation upgrades—prompting mandatory 80%–85% minimum demand ratchets in Ohio, Virginia, Indiana, Georgia, and Texas.
05_Time_To_Power_Waitlist5. 'Time-to-Power' Substation Waitlist Indexmart.large_load_master, core.substation_upgrade303.7 GW across Top 25 Hubs (34–52m Wait)The top 25 most congested U.S. substation corridors hold 303.7 GW of stacked data center load requests, facing an average queue dwell time of 27.2 months and EHV transformer delivery lead times of 34–52 months (pushing new energizations to 2028–2030).
06_Moratoria_And_Subsidies6. Moratorium, Pushback & Tax Subsidy Ledgercore.local_public_pushback, deal.v_verified_pilot_incentives112 Pushback Hubs vs. 8 Statutory PILOTsAIxEnergy tracks 112 active municipal pushback & moratorium flashpoints alongside 55 restrictive local zoning/grid policy regimes—even as pro-growth jurisdictions approved $50.4B in statutory PILOT tax-abatement megadeals tied to strict job and CapEx clawbacks.

Worksheet 00_Executive_Brief_And_Quotes in the 2026-W46 workbook.

Table 1 · 10 rows

The weekly AI power rig count

Large-load (data center and AI) interconnection requests in grid queues, by grid operator: how many requests, how much capacity they ask for, the change since the previous weekly queue snapshot, and how much of it AIxEnergy's ELL-2.2.0 model expects to be built.

  • Gross Active Queue1,136.83 GW4,351 projects
  • Weekly Net Change+4,425 MW+0.39% WoW
  • Realization-Adjusted284.22 GW25.0% P-Eventual
  • Phantom/Speculative Share75.0%852.6 GW
Quotable lead

U.S. & North American grid operators tracked 1,136.8 GW of active large-load AI & data center requests across 4,351 queue positions this week (+4,425 MW WoW), though AIxEnergy's ELL-2.2.0 realization model projects only 284.2 GW (25.0%) will ultimately energize (19.5%–32.5% across ISOs)—leaving 75.0% (852.6 GW) as phantom, speculative, or policy/pushback-blocked requests.

Notes. Gross figures are requested capacity. Realization-adjusted figures and the phantom share are model estimates, not grid-operator forecasts. The last row is the total.

Preview the first 6 of 10 rows (12 columns)
ISO / Grid OperatorActive Queue PositionsGross Requested (GW)WoW Net Change (MW)WoW Change (%)Realization-Adjusted (GW)Mean P(Eventual) (%)Phantom Queue Share (%)Committed / Construction (GW)Energized Operating (GW)30-Day Withdrawn (MW)Median Queue Dwell (Mos)
ERCOT798269.914800.5557.2221.278.838.424.768534
PJM1341265.589200.3572.7727.472.652.145.39430.946
NYISO861169.913100.1833.1319.580.518.455.6234542
MISO261129.116400.534.626.873.224.811.1828038
SERC41698.164200.4331.932.567.522.615.5919532
WECC21773.282900.420.3727.872.214.59.96179.240

Worksheet 01_Weekly_AI_Power_Rig_Count in the 2026-W46 workbook.

Table 2 · 16 rows

The hyperscaler power scoreboard

The 15 largest sponsors of data center campuses in the AIxEnergy project database, ranked by total pipeline load, with construction status, disclosed and committed capital spending, and contracted nuclear and geothermal supply.

  • Top 15 Total Pipeline306.59 GW1,665 campuses
  • Under Construction124.72 GW Active Build
  • Disclosed CapEx$2,989.1B$1,724.5B Committed
  • Contracted Nuclear/Geo15.28 GW Firm Clean
Quotable lead

The top 15 hyperscalers and AI infrastructure developers now control 306.6 GW of active data center power pipeline backed by $2,989.1B in disclosed capital commitments ($9.75M/MW avg intensity) and 15.28 GW of contracted nuclear & firm geothermal baseload.

Notes. Campuses are attributed to sponsors by matching developer, operator and customer names. GPU capacity is an estimate. The last row is the total.

Preview the first 6 of 16 rows (11 columns)
RankHyperscaler / Sponsor OrganizationTracked CampusesTotal Pipeline Load (GW)Under Construction / Committed (GW)Energized Operating (GW)Disclosed CapEx ($B)Committed CapEx ($B)CapEx Intensity ($M/MW)Contracted Nuclear & Geo (MW)Est. B200-Eqv GPU Capacity
1Microsoft13752.4220.764.31568.77223.1610.852905224,800
2Oracle / OpenAI (Stargate)3634.0323.250.26425.4239.8212.51650165,000
3Amazon / AWS27633.116.486370.76211.3311.22920294,500
4Tract (Master Planned Parks)1629.424.054.0563.2522.862.15015,000
5Meta Platforms7827.0118.156.16280.87212.6910.42450142,000
6Alphabet / Google9520.6812.353.31220.27142.5310.651865188,400

Worksheet 02_Hyperscaler_Power_Scoreboard in the 2026-W46 workbook.

Table 3 · 22 rows

Megadeal and county land-deed log

Verified county land deeds for data center sites, with buyer, seller, county, amount, acreage and price per acre, alongside capital-spending announcements of $1 billion or more. Each row carries its filing or source citation.

  • Verified Land Deeds$1,943.6M10 deeds
  • Total Conveyed Acreage10,349.5 Acres
  • Weighted Avg Land Price$187,797 / Acre
  • Megadeal CapEx Filings12 Transactions ≥ $1.0B
Quotable lead

Verified county recorder deeds tracked $1,943.6M in hyperscaler land acquisitions across 10,350 acres (averaging $187,797/acre), led by Amazon's $650M Susquehanna nuclear campus deed and Microsoft's $215M Loudoun assemblage.

Notes. Deed amounts are as recorded; megadeal amounts are as announced by the sponsor.

Preview the first 6 of 22 rows (11 columns)
Recording / Filing DateTransaction TypeProject / Campus NameBuyer / Sponsor EntitySeller / CounterpartyCounty & StateVerified Amount ($M)Conveyed AcreagePrice per Acre ($/Ac)Associated Campus MWStatutory Instrument / Filing Citation
2026-11-09LAND DEED RECORDINGAWS Madison County Mega Data Center CampusAmazon Data Services, Inc.Madison County Economic Dev. AuthorityMadison County, MS126920136,9571300INST-2026-44109 (BK-4215/PG-0118)
2026-11-04LAND DEED RECORDINGStargate Abilene (Crusoe / Oracle / OpenAI Campus)Crusoe / Oracle Stargate JV LLCLancium Clean Campus LLCTaylor County, TX1841100167,2731400DOC-2026-110482 (OPR-2026/PG-5501)
2026-10-28LAND DEED RECORDINGGoogle Buckeye / West Valley AI CampusGoogle LLC (Sidewinder Acquisition LLC)Buckeye Valley Holdings LLCMaricopa County, AZ178740240,5411000MCR-2026-0841920 (BK-2026/PG-8419)
2026-10-22LAND DEED RECORDINGMicrosoft Mount Pleasant AI Supercomputing CampusMicrosoft CorporationVillage of Mount Pleasant CDARacine County, WI99.7103096,7961200DOC-2694812 (VOL-4810/PG-305)
2026-10-14LAND DEED RECORDINGAWS New Carlisle Mega Data Center CampusAmazon Data Services, Inc.New Carlisle Industrial Corridor LLCSt. Joseph County, IN134880152,2732200INST-2026-29410 (BK-2026/PG-0912)
2026-10-04LAND DEED RECORDINGMicrosoft Compass / Dulles South CampusMicrosoft Corporation (SI Va LLC)Dulles South Land Holdings LLCLoudoun County, VA215342628,655600INST-20261004-0051820 (BK-4120/PG-0881)

Worksheet 03_Weekly_Megadeal_Deed_Log in the 2026-W46 workbook.

Table 4 · 23 rows

Ratepayer cost exposure and utility tariff watch

The 22 utilities with the most large-load capacity requested, how much of it is expected to materialize (and within 24 and 60 months), an estimate of the grid-upgrade cost involved, and the docket or tariff that decides who pays.

  • Top 22 Utilities Queue716.15 GW Gross Requested
  • Realization-Expected Load171.98 GW Expected
  • Substation/Tx Exposure$39.16B Tracked Upgrades
  • Dominant Tariff Rule80–85% Min Demand / 12–20 Yr Term
Quotable lead

Across the top 22 U.S. electric utilities facing 716.1 GW of large-load requests, regulators are tracking $39.16B in required transmission and substation upgrades—prompting mandatory 80%–85% minimum demand ratchets in Ohio, Virginia, Indiana, Georgia, and Texas.

Notes. Expected-load columns come from the ELL-2.2.0 model. Upgrade-cost estimates and the docket and tariff descriptions are AIxEnergy analyst assignments for each utility, not totals taken from utility filings. The last row is the total.

Preview the first 6 of 23 rows (10 columns)
ISO / RTOElectric Utility / Transmission OwnerActive Load RequestsGross Queued Load (GW)Realization-Expected Load (GW)24-Month Expected (GW)60-Month Expected (GW)Est. Grid Upgrade Exposure ($M)Key Regulatory DocketRatepayer Protection & Tariff Mechanism
ERCOTOncor Electric Delivery434137.9729.2515.7927.493420PUCT 57152 / ERCOT SB 6100% Substation CIAC Deposit + ERCOT Study
PJMDominion Energy Virginia50968.7518.8410.1717.714850VA SCC PUR-2024-0014414-Yr Contract / 85% T&D Demand Ratchet
NYISONational Grid (Upstate NY)31963.1612.326.6511.581120NYPSC Case 24-E-0364Upfront 345 kV Transmission Security Deposit
NYISONew York Power Authority (NYPA)13149.259.65.199.03620NYPA Large Load AllocationStatutory Industrial Hydro Allocation Cap
MISOEntergy (Louisiana / Mississippi / Texas)2342.8211.486.210.792250LA PSC U-37425 / MS PSCDedicated CCGT Generation & 500/345 kV Rider
PJMCommonwealth Edison (ComEd)18840.6611.146.0210.471680ICC Large Load Rider TS10-Yr Minimum Capacity Commitment & CIAC

Worksheet 04_Ratepayer_Cost_Exposure in the 2026-W46 workbook.

Table 5 · 25 rows

Time-to-power: substation bottlenecks

The 25 substation corridors with the most data center load stacked in the queue, with voltage, number of requests, gross and realization-adjusted load, and the expected wait to connect.

  • Top 25 Bottleneck Hubs303.74 GW Stacked Load
  • Realization-Expected Load71.59 GW Realized
  • Mean Queue Dwell Time27.2 Months
  • EHV Upgrade Lead Time34–52 Months2028–2030 COD
Quotable lead

The top 25 most congested U.S. substation corridors hold 303.7 GW of stacked data center load requests, facing an average queue dwell time of 27.2 months and EHV transformer delivery lead times of 34–52 months (pushing new energizations to 2028–2030).

Notes. Queue dwell, equipment lead times, target energization windows and the bottleneck descriptions are AIxEnergy engineering estimates for each corridor.

Preview the first 6 of 25 rows (12 columns)
RankISO / RTOHost UtilitySubstation / POI CorridorVoltage (kV)Stacked RequestsGross Queued Load (GW)Realization-Adjusted Load (GW)Avg Queue Dwell (Mos)Upgrade Lead Time (Mos)Target Energization WindowPrimary Physical Grid Bottleneck
1ERCOTTexas-New Mexico Power CompanySolstice / Reeves-Pecos 345kV Permian Hub3452848.2310.2224.540Q1 2029Permian 345/765kV Dynamic Reactive & Series Compensation
2MISOEntergy LouisianaRichland 345kV Hub5006308.0419.836Q4 2028500/230kV Autotransformer Bank & Dedicated CCGT Tie
3ERCOTOncor Electric DeliverySweetwater / Nolan County 345kV CREZ Hub3452826.45.626.238Q2 2029West Texas CREZ 345kV Thermal Export & Short-Circuit Limit
4PJMNOVEC (Northern Virginia Electric Cooperative)Loudoun 345kV Hub50020018.285.0138.652Q4 2030500/230kV GIS Breaker Bay & Golden-Mars 500kV Loop
5PJMAEP OhioPike 345kV Hub3452164.3827.842Q3 2029Piketon 345kV Portsmouth-Don Marquis Loop Thermal Limit
6ERCOTBluebonnet Electric Cooperative (LCRA)Caldwell 345kV Hub3453122.5422.438Q2 2029LCRA-Bluebonnet 345kV Lockhart Switching Station

Worksheet 05_Time_To_Power_Waitlist in the 2026-W46 workbook.

Table 6 · 23 rows

Moratoria, local pushback and tax subsidies

Local moratoria and public-pushback actions against data centers, set against statutory PILOT tax-abatement deals and the minimum capital spending and jobs they require.

  • Civic Pushback Flashpoints112 Tracked Jurisdictions
  • Restrictive Policy Regimes55 Local Ordinances/Rules
  • Verified PILOT Megadeals8 Statutory Awards
  • Clawback-Backed CapEx$50.4B Committed
Quotable lead

AIxEnergy tracks 112 active municipal pushback & moratorium flashpoints alongside 55 restrictive local zoning/grid policy regimes—even as pro-growth jurisdictions approved $50.4B in statutory PILOT tax-abatement megadeals tied to strict job and CapEx clawbacks.

Notes. The headline counts of pushback flashpoints and restrictive policy regimes cover AIxEnergy's full tracker; the table lists a selection of them.

Preview the first 6 of 23 rows (10 columns)
Ledger CategoryJurisdiction & StateAction / Approval DateTarget Campus / ProjectDeveloper / SponsorAction Type / Abatement TermsLegal Status / Ordinance CitationClawback Min CapEx ($B)Min Jobs RequirementSummary & Policy Impact
CIVIC PUSHBACK / MORATORIUMWashtenaw County, Michigan2026-09-24Saline Township data center / Stargate-related proposalRelated project entitiesPublic hearingTownship planning commission tabled the rezoning request for 60 days to solicit additional grid studies——Residents filled the township hall to oppose a proposed 120 MW computing center, challenging rezoning from light industrial and highlighting DTE electric substation expansion and noise near residential subdivisions.
CIVIC PUSHBACK / MORATORIUMTravis County, Texas2026-09-21Multiple Proposed CampusesMultiple DevelopersRally or protestGovernor issued directive halting all new TCEQ data center permits hours after petition delivery——A coalition of ratepayer advocacy and conservation groups delivered thousands of petition signatures to the Texas Capitol highlighting ERCOT grid strain and Hill Country groundwater depletion from rapid data center buildouts, preceding Governor Abbott's directive halting TCEQ permits.
CIVIC PUSHBACK / MORATORIUMMontgomery County, Maryland2026-08-10New Montgomery County data centersMultiple / prospectiveGovernment responseBuilding-permit pause enacted——Expedited Bill 19-26 was signed August 10 after an 11–0 council vote, establishing a moratorium on data-center building permits in Montgomery County, Maryland.
CIVIC PUSHBACK / MORATORIUMLyon County, Kansas2026-11-03Emporia data-center proposalProject applicantBallot referendumBoth 10-year municipal bans approved by voters on Nov 3, 2026——On November 3, 2026, voters in Emporia (~60% yes) and El Dorado (~71% yes) approved citizen-petitioned ballot initiatives enacting 10-year bans on high-impact data centers exceeding 10 MW of electric load or 100,000 gallons of daily water consumption, as well as large battery storage systems.
CIVIC PUSHBACK / MORATORIUMMiddlesex County, New Jersey2026-09-23Princeton Nurseries Data CenterPrinceton Digital InfraLegal challengeLawsuit filed; expedited injunction hearing set for November 2026——Community groups filed suit in state court challenging air quality permits issued for 36 backup diesel generators at a proposed data center campus, citing PM2.5 pollution near elementary schools and noise violations under local decibel limits.
CIVIC PUSHBACK / MORATORIUMPrince William County, Virginia2026-09-22Prince William Digital GatewayQTS and Compass DatacentersGovernment responseBy-right status abolished; SUP mandatory; overlay reduced from ~9,700 to 3,641 acres——Following months of grassroots organizing, yard sign campaigns, and extensive public testimony, coalition leaders secured an 8-0 Board of Supervisors vote stripping by-right development privileges from data centers and shrinking the county overlay district by over 6,000 acres.

Worksheet 06_Moratoria_And_Subsidies in the 2026-W46 workbook.

Table 7 · 52 rows

Nuclear, SMR and geothermal deal tracker

Contracts and announced pairings between data center operators and nuclear plants, small modular reactors and enhanced-geothermal projects: plant, offtaker, technology, contracted megawatts, regulatory stage, target operating date and a state nuclear-policy score.

  • Nuclear & SMR Contracted38.53 GW37 plants
  • Geothermal (EGS) Deals1,444 MW14 pairings
  • Total Clean Firm Baseload39.97 GW
  • State Nuclear Regimes51 States/DC ScoredTiers 1–5
Quotable lead

Hyperscalers have now contracted 38.53 GW across 37 nuclear & SMR plants plus 1,444 MW across 14 next-generation geothermal (EGS) pairings (39.97 GW total firm 24/7 clean baseload).

Notes. Contracted MW includes planned and announced deals, not only operating supply. The last row is the total.

Preview the first 6 of 52 rows (16 columns)
Clean Firm PillarDeal CategoryPlant / Resource NameGenerator / Developer OwnerData Center OfftakerPaired Data Center CampusState / ProvinceISO / Grid RegionReactor / Resource TechnologyDelivery Mode (BTM / FTM)Contracted / Planned MWOperating Plant MWStage / Regulatory StatusTarget CODState Nuclear Policy TierState Policy Score
NUCLEAR / SMRAdvanced SMR — Master Power AgreementOklo × Switch 12 GW Aurora Fast Reactor Master Power Agreement FleetOklo Inc.Switch, Inc.Switch Citadel Campus (Tahoe-Reno), Las Vegas Core Campus, Atlanta Keep & Texas RockNVNEVPLiquid Metal-Cooled Fast Reactor (Oklo Aurora 15–75 MWe Modular Fast Reactors)Behind-the-Meter (BTM) Co-Located & Grid-Connected Corporate PPAs12,0000Announced / Master Framework Agreement (Site-specific PPAs in development)Late 2020s–2044 Phased RolloutTier 3: Coal-to-Nuclear / SMR Enabling68
NUCLEAR / SMRLarge-Scale Gen III+ Nuclear — Co-Located AI MegacampusProject Matador Nuclear Station (Fermi America HyperGrid 4 × AP1000)Fermi Nuclear LLC (Fermi America / Texas Tech University System)Fermi HyperGrid AI Campus & TensorWave Phase 1 (Amarillo / Carson County TX)Fermi HyperGrid Campus & Fermi Project Matador – TensorWave Phase 1TXSWPP / ERCOTPressurized Water Reactor (4 × Westinghouse AP1000 Gen III+)Behind-the-Meter (BTM) Co-Located at Pantex / Texas Tech Research Park44680Planned / NRC Combined License (COL) Application Accepted for Review (2025)2032 (Unit 1 target); mid-2030s (4-unit buildout)Tier 1: Flagship Accelerator96
NUCLEAR / SMROperating Nuclear Fleet — Co-Located / FTM PPASusquehanna Steam Electric Station Units 1 & 2Talen Energy Corporation (Susquehanna Nuclear, LLC)Amazon Web Services (AWS)AWS Salem Township AI Data Center Campus (Cumulus Site at Susquehanna)PAPJMBoiling Water Reactor (2 × GE BWR-4 / Mark II)Co-Located BTM transitioning to Front-of-the-Meter (FTM) via PPL Electric (Spring 2026)19202532Operational (Units 1 & 2 online 1983/1985; FTM Reconfiguration 2026)Operational (Full 1,920 MW ramp by 2032)Tier 2: Pro-Nuclear Fleet & ZEC / Restart88
NUCLEAR / SMRAdvanced SMR — Shipyard-Fabricated BTM AI CampusPort of Victoria Modular Nuclear Power Plant (Blue Energy × Crusoe)Blue Energy Inc.Crusoe Energy Systems LLCCrusoe Port of Victoria AI Data Center Campus (Victoria County, TX)TXERCOTSmall Modular Reactor (Shipyard-Manufactured Light-Water / BWRX-300 Class Modular Plant)Behind-the-Meter (BTM) Co-Located (Gas-to-Nuclear Phased Transition)15000Announced / Site Leased at Port of Victoria (NRC Pre-Application)2031 (Nuclear Phase; Gas Bridge 2028)Tier 1: Flagship Accelerator96
NUCLEAR / SMROperating Nuclear Fleet — Long-Term PPA + UpratePerry Nuclear Power Plant Unit 1Vistra Corp. (Energy Harbor Nuclear Corp.)Meta Platforms, Inc.Meta New Albany & Prometheus Supercluster AI Data Center Campuses (Central Ohio)OHPJMBoiling Water Reactor (GE BWR-6 / Mark III)Grid-Connected (PJM ATSI Zone)12681311.6Operational (Online 1987; Uprate in engineering for early 2030s)Operational (Meta PPA starts late 2026; uprates through 2034)Tier 2: Pro-Nuclear Fleet & ZEC / Restart84
NUCLEAR / SMROperating Nuclear Fleet — Co-Located / Long-Term PPAComanche Peak Nuclear Power Plant Units 1 & 2Vistra Corp. (Luminant Generation Company LLC)Amazon Web Services (AWS)Comanche Peak Nuclear Data Center ('Project Spectrum' — Hood/Somervell TX)TXERCOTPressurized Water Reactor (2 × Westinghouse 4-Loop PWR)Grid-Connected ERCOT + Co-Located Somervell County Site ('Project Spectrum')12002430Operational (Units 1 & 2 online 1990/1993; NRC licensed through 2050/2053)Operational (1,200 MW PPA delivery ramps Q4 2027 – Q4 2032)Tier 1: Flagship Accelerator96

Worksheet 07_Nuclear_Geothermal_Deals in the 2026-W46 workbook.

Table 8 · 24 rows

Wholesale power prices in AI hub zones

Average 2026 day-ahead, real-time and load-weighted wholesale power prices in 24 pricing zones with heavy data center development, the change from 2025, the technology that most often sets the marginal price, and its carbon intensity.

  • Tracked AI Hub Zones24 Pricing Zones9 ISOs
  • 2026 Load-Weighted LMP$51.24 / MWh
  • Mean YoY Price Escalation+8.7% YoY2026 vs. 2025
  • Dominant Marginal FuelNatural Gas CC/CT60.2% hours
Quotable lead

Across the 24 primary North American AI data center pricing zones (spanning all 9 ISOs), load-weighted wholesale electricity prices averaged $51.24/MWh in 2026 (+8.7% YoY, led by PJM Dominion at +14.8% and ERCOT West at +12.4%), with natural gas and dual-fuel units setting the marginal price in 60.2% of hours.

Notes. Marginal CO₂ intensities are zone-level reference values. Where a zone has no 2025 annual figure, the 2025 price is back-estimated.

Preview the first 6 of 24 rows (12 columns)
ISO / RTOZone IDPricing Zone / AI Hub Name2026 Avg Day-Ahead LMP ($/MWh)2026 Avg Real-Time LMP ($/MWh)2026 Load-Weighted LMP ($/MWh)2025 Load-Weighted LMP ($/MWh)YoY LMP Change (%)Total Zone Cost Exposure ($B)Dominant Marginal TechnologyMarginal Tech Share (%)Marginal CO2 Intensity (kg/MWh)
PJMPJM_DOMDominion Virginia (Data Center Alley)68.5670.471.462.214.89.45NG_CC64.2418
MISOMISO_LRZ9MISO LRZ 9 (Louisiana & East Texas)56.3356.6758.2353.329.28.51NG_CC74.8402
ERCOTERCOT_NORTHERCOT North Hub (DFW / Abilene)49.3850.7152.847.411.47.84NG_CC68.5394
PJMPJM_AEPAEP Ohio / Appalachian Zone51.252.8554.147.6213.67.42COAL_NG61.8568
MISOMISO_LRZ7MISO LRZ 7 (Michigan Lower Peninsula)54.5954.9756.4252.487.57.25NG_CC66.4472
PJMPJM_COMEDCommonwealth Edison (Northern Illinois)46.848.1549.7845.110.46.48NG_CC57.6356

Worksheet 08_Wholesale_Price_Pulse in the 2026-W46 workbook.

Archive

Every release

Each Monday's release is added here. Files from earlier weeks stay at the same addresses and are not changed after publication, so a figure you cite can always be traced back to its file.

WeekAs ofModelExcelZIPSHA-256
2026-W46 (latest)November 15, 2026ELL-2.2.0WorkbookAll files37c31d504053…

This is the first published release.

For journalists

How to use and cite this data

Which file should I download?
Excel if you want the formatted tables with their headline banners; CSV for spreadsheets, Datawrapper, Flourish or code; JSON if you are building something. CSV and JSON files hold only the data rows under a single header row.
How should I cite it?
Name the release week, so readers can find the exact file:
AIxEnergy Weekly Media Benchmark, 2026-W46 (data as of November 15, 2026). AIxEnergy. https://aixenergy.io/benchmarks/
Which figures are estimates?
Anything labeled realization-adjusted, expected, P(eventual) or phantom comes from the ELL-2.2.0 model and should be described as an AIxEnergy estimate. Gross queue figures are requested capacity, not demand that will appear on the grid. Each table's notes flag analyst-assigned columns.
When is it updated?
Every Monday morning, US Eastern time. Releases are labeled by ISO week (for example 2026-W46); the as-of date is the last day of that week. Earlier releases stay in the archive.
Can I check a file has not been altered?
Yes. Each workbook's SHA-256 checksum is listed above and in the archive, and the ZIP includes checksums for every file inside it.
Questions, corrections or interviews
Email bowens@aixenergy.io (Brandon N. Owens, Chief Executive Officer, AIxEnergy). Please include the release week and table number.
Methodology

How the figures are produced

What the benchmark is

The AIxEnergy Weekly Media Benchmark is a set of standardized tables on electricity demand from data centers and AI, drawn each week from the AIxEnergy database. That database combines grid-operator and utility large-load queue records, project and capital-spending records, county land deeds, local policy and public-pushback records, nuclear and geothermal supply deals, and wholesale market prices.

Gross versus realization-adjusted load

Interconnection queues overstate what will be built: developers file in several places at once, and many requests are speculative or are stopped by cost, policy or local opposition. Gross figures report capacity as requested. Realization-adjusted figures weight each request by its estimated probability of eventually being energized under AIxEnergy's ELL-2.2.0 large-load realization model. The difference between the two is reported as the phantom or blocked share.

The ELL-2.2.0 model

ELL-2.2.0 assigns each large-load request a probability of eventual energization, and probabilities of energization within 24 and 60 months. It runs as a national model with separate versions for nine grid regions (ERCOT, PJM, MISO, SPP, CAISO, NYISO, BPA/Northwest, WECC Southwest/Mountain and SERC), each reflecting that region's queue rules, collateral and tariff requirements, local moratoria and public pushback. Its regional realization rates currently range from 19.5% to 32.5%. Its outputs are estimates, not forecasts by grid operators or utilities, and should be reported as AIxEnergy estimates.

Analyst inputs

Some columns are AIxEnergy analyst or engineering assignments rather than database records: utility grid-upgrade cost estimates and the docket and tariff descriptions in table 4; queue dwell, equipment lead times, target windows and bottleneck descriptions in table 5; and marginal carbon intensities in table 8. Each table's notes say which.

Release cadence and integrity

A new release is published each Monday morning (US Eastern time), labeled by ISO week; the as-of date is the last day of that week. Each workbook carries a SHA-256 checksum, and files from earlier weeks stay available in the archive unchanged. Week-over-week changes on this page compare a release with the previous one in the archive.