AI Data Center Power Demand, Week 46, 2026 (Permalink)

Figures as published for week 46, 2026, data as of November 15, 2026: 175.40 GW of AI and data center load queued for the grid; AIxEnergy's ELL-2.2.0 model expects 43.85 GW to be built.


Share this post
Permalink

Week 46, 2026 figures as published

This page keeps the 2026-W46 figures for citation. Revised November 15, 2026 (All tables restated from a reissued source workbook that adds row-level source URLs and retrieval dates (new worksheet 09). Scope and definitions changed: Table 1 now covers active U.S. ISO large-load positions (gross queue 175.40 GW, previously 1,136.83 GW); Table 3 lists verified capital filings in place of land deeds; Table 8 headline is the 2025 load-weighted price ($49.98/MWh, previously a 2026 simple average of $51.24).). Latest week, tables and methodology: AI data center power demand benchmarks.

  • Large-load queue, gross175.40 GWObserved Capacity requested in U.S. ISO queues.
  • Expected to be built43.85 GWModeled ELL-2.2.0 estimate of the queue that reaches service.
  • Phantom or blocked share75.0%Modeled Requested capacity the model treats as speculative or blocked.
  • Top-15 sponsor pipeline108.42 GWObserved Planned and active load at the 15 largest sponsors' campuses.
  • Disclosed capital, top 15$654.56bnObserved Capital stated in company filings.
  • Modeled build-out cost, top 15$1,119.91bnModeled Pipeline GW × assumed cost per MW; not company-disclosed.
  • Verified capital filings$153.77bnObserved Campus capital commitments verified against filings.
  • Queue at named utilities89.60 GWObserved Share of the Table 1 queue held by named utilities.
  • Load at top-25 corridors50.83 GWObserved Requested load at the 25 named corridors.
  • Local pushback flashpoints112 jurisdictionsObserved Places opposing, pausing or restricting projects.
  • Restrictive local policies987 rulesObserved Moratoria, ballot bans and zoning constraints.
  • Nuclear, SMR and geothermal contracted18,702 MWObserved Contracted supply for data centers; planned MW excluded.
  • Wholesale price, 24 AI hub zones$49.98/MWhObserved 2025, weighted by zonal load.
Findings

Week 46, 2026 in brief

  • U.S. ISO large-load queues hold 175.40 GW of data center and AI requests (467 positions, 9 grid operators), +18.17 GW since the October 1, 2026 snapshot. Table 1, Excel
  • AIxEnergy's ELL-2.2.0 model expects 43.85 GW of that load to be built; 75.0% is speculative or blocked. Table 1, Excel
  • The 15 largest sponsors have a 108.42 GW pipeline across 568 campuses, with $654.56bn of capital disclosed in filings; the modeled build-out cost is $1,119.91bn (AIxEnergy estimate). Table 2, Excel
  • 20 verified campus capital filings total $153.77bn for 17,549 MW of disclosed load. Table 3, Excel
  • AIxEnergy tracks 112 local pushback flashpoints and 987 restrictive local policies on data centers. Table 6, Excel
  • 18,702 MW of nuclear, SMR and geothermal supply is contracted to data centers (37 nuclear plants, 14 geothermal pairings). Table 7, Excel
  • Wholesale power in 24 AI data center pricing zones averaged $49.98/MWh in 2025, weighted by zonal load (simple average $49.33/MWh). Table 8, Excel
Files

Download 2026-W46

SHA-256, published workbook
35e8d8253b909c8ca481774e5d1cddf414adf7b988f7f9cd9ea54791fd01f0bb
SHA-256, database workbook
71a35f06c23a941345626e338a00785d716c6f31f2456658ff94c7f15d930411
Model
ELL-2.2.0
Superseded workbook, November 15, 2026
Excel 6e928b3b1cbc8180ee175a338c6b6e86829fb7e3f0964ca8e6771e7efcdecce6
Cite as
Source: AIxEnergy (aixenergy.io/benchmarks), Weekly Media Benchmark 2026-W46, data as of November 15, 2026. CC BY 4.0.
Cite or embed a figure13 figures; embed code has no scripts or tracking