- Three nuclear deals that Google, Meta and Amazon announced in PJM in 2026 cover 6,889 megawatts. Only 1,513 megawatts, or 22 percent, are planned uprates that add output; the rest buys existing power or financial coverage.
- Restarts are different. Crane in Pennsylvania (835 megawatts) and Duane Arnold in Iowa (615 megawatts) would return idle reactors to the grid, backed by technology buyers and federal loans.
- States set the terms. Georgia routes Google's payments back to customers, while New Jersey withholds state support from output sold directly to a data center.
- Agreements with the advanced reactor developers Oklo, TerraPower, Kairos and X-energy mostly fund fuel, early development and first-of-a-kind plants, years before any of them delivers power at scale.
On November 20 the U.S. Department of Energy ordered two dual-fuel units at Pennsylvania's Eddystone station to remain available to the grid through February. Both had been due to retire in May 2025. By the time the order arrived, their owner, Constellation Energy, had already handed their capacity interconnection rights, the grid-access rights that let a plant sell capacity, to a different plant. That plant, the former Three Mile Island Unit 1, had been shut since 2019. Its prospective customer is Microsoft.1
Microsoft had agreed to buy the output of the restarted reactor for 20 years. Constellation had secured a $1 billion federal loan and was aiming to bring 835 megawatts back in 2027. Then a study by PJM, the regional grid operator, identified transmission upgrades that could delay full delivery until as late as December 2030. In June federal regulators allowed the transfer. Eddystone could still run when dispatchers called on it, while the capacity rights would help the reactor, now called the Crane Clean Energy Center, deliver sooner.2
Microsoft is buying electricity that Pennsylvania has gone seven years without. Most corporate nuclear deals are harder to read. A company buying power from a working reactor may give its owner enough revenue to keep it open. A financial contract can protect a data center against a rise in wholesale prices while leaving every generator on the system running exactly as before. Each agreement is quoted in megawatts, the same unit a utility uses to say how much new demand it can serve.
AIxEnergy compared three purchases announced by Google, Meta and Amazon in 2026 in PJM, which serves much of the Mid-Atlantic and parts of the Midwest. Together the companies disclosed 6,889 megawatts of purchases and financial coverage. Of those, 1,513 megawatts, or 22 percent, represent planned increases in the output of operating reactors. Another 2,676 megawatts are purchases associated with existing output. The remaining 2,700 belong to a financial agreement between Google and Constellation. A planner reading the three headline figures as additions to supply would be looking for nearly 5,400 megawatts that the agreements never promised to build.3
Table 1
How three PJM deals divide 6,889 megawatts
| Buyer and seller | Existing output | Financial coverage | Planned uprates | Total volume |
|---|---|---|---|---|
| Google / Constellation | – | 2,700 | 890 | 3,590 |
| Meta / Vistra | 2,176 | – | 433 | 2,609 |
| Amazon / Constellation | 500 | – | 190 | 690 |
| Total, MW | 2,676 | 2,700 | 1,513 | 6,889 |
All figures in megawatts. Existing output at Calvert Cliffs is the 690-megawatt agreement less its 190-megawatt uprate. Totals measure the volume covered by the agreements, not additions to supply. Sources: AIxEnergy calculations from the companies' announcements and filings (note 3).
A second customer for the same turbine
Google signed two agreements with Constellation on October 6. One runs for 20 years and supports improvements at 11 reactor units at six sites in Illinois, Pennsylvania and New Jersey. Constellation expects the first uprate, as an increase in a plant's rated output is known, in 2028. Google expects the full 890 megawatts by the end of 2032. The other agreement runs for 15 years. Constellation describes it in its quarterly filing as a financial contract covering 2,700 megawatts that follows Google's electricity load. A financial settlement can be valuable to a buyer with a large power bill even if it never causes a turbine to turn faster.4
Constellation puts the investment associated with Google's uprates at more than $4.3 billion, which works out to more than $4,800 per kilowatt of added capacity. The companies disclosed what Constellation expects to spend. They kept the price Google will pay per megawatt-hour private. At Maryland's Calvert Cliffs, Constellation expects to invest more than $3 billion under a deal with Amazon. Dividing that entire sum by the 190 megawatts of added output would charge the uprate for improvements across a 1,790-megawatt station. In October the Energy Department offered Constellation a conditional loan of up to $5 billion for uprates and modernization across its fleet in three states. The loan would help pay for the work. Adding its face value to the investment figures would count some of the same money twice.5
Vistra's agreement with Meta has two delivery schedules. The 2,176 megawatts of existing capacity come from Perry and Davis-Besse in Ohio. Of the 433 new megawatts, Vistra assigns 213 to Perry, 80 to Davis-Besse and 140 to Beaver Valley in Pennsylvania. Vistra's published schedule puts the first purchases from the operating fleet in late 2026 and the first deliveries from the uprates by 2031, with the upgrades fully in service by the end of 2034. A utility expecting a new data hall in 2028 must find another source for any load it had counted on those uprates to cover.6
The plant next door
The AIxEnergy inventory contains 43 records, ranging from individual plants to proposals for whole fleets of reactors. The accompanying survey of state policies covers all 50 states and the District of Columbia. In Wisconsin, two projects on the western shore of Lake Michigan show why a map needs both a buyer's name and the quantity it agreed to buy.7
A University of Wisconsin presentation put Vantage's Lighthouse campus, under construction in Port Washington, at 902 megawatts. In October Oracle announced plans to subscribe to power from Point Beach through We Energies. Wisconsin Public Radio reported a range of 125 to 250 megawatts. In August Wisconsin Electric, the utility operating as We Energies, had separately agreed, subject to regulatory approval, to buy 86 percent of the output of both reactors once their existing contracts expire in 2030 and 2033. The first figure describes a campus and the second a proposed subscription, while the third is a utility's long-term purchase. All three refer to the same stretch of shoreline.8

At Susquehanna in Pennsylvania, the data center really is next door. In 2024 PJM asked the Federal Energy Regulatory Commission to accept an amendment increasing the load that could be served under the plant's existing interconnection agreement from 300 to 480 megawatts. The commission rejected the amendment that November. In June 2025 Talen Energy and Amazon struck a larger bargain. Talen would supply as much as 1,920 megawatts from Susquehanna by 2032, with deliveries extending through 2042. The arrangement provides for the plant to sell into PJM, Talen to act as Amazon's retail supplier, and PPL Electric Utilities to deliver the power. Amazon can use it at other Pennsylvania locations as well.9
Talen exchanges some of its exposure to wholesale prices for a long-term customer. Amazon gains room to expand across the state. What Amazon pays for access to the network matters to everyone who shares it. If a reactor comes offline and the campus wants to keep drawing power, the utility must have enough capacity available to serve it. A customer willing and able to cut demand at those times makes a smaller claim on the network, provided its control systems and its service agreement make that promise credible. In a November 16 filing, PJM proposed firm and non-firm transmission service at specified levels of demand and a process to study new generators and large loads together. A campus that requires firm backup will be buying a service from the grid even on days when the neighboring plant supplies all the energy it needs.10
At Comanche Peak in Texas, Vistra agreed in 2025 to supply Amazon with 1,200 megawatts for 20 years. The company expects deliveries to start in the fourth quarter of 2027 and to reach the full amount by 2032. Vistra's contract sets the pace at which Amazon buys power from machines already serving the Texas market. A Texas planner who adds 1,200 megawatts of generation to the supply forecast on the strength of that agreement would count the same plant twice.11
Who pays to bring a reactor back
Iowa's Duane Arnold Energy Center illustrates the opposite accounting error. The 615-megawatt plant shut in 2020. Google's 25-year purchase agreement helped make a restart possible, and the Energy Department closed a loan of up to $1.9 billion in September. NextEra Energy is targeting the first quarter of 2029, subject to regulatory approvals. If the plant returns, the regional system regains 615 megawatts. Google's share comes to about 565. Central Iowa Power Cooperative agreed to take 50 on the same terms. The cooperative also sold its ownership stake. Its chief executive told members in November that they had exchanged a decommissioning obligation for the right to buy electricity at a fixed price. Google is helping Iowa recover a power plant. The cooperative used the same transaction to get out of the business of owning one.12
Michigan's Palisades plant is another of the few American reactors being brought back from retirement. Its named power buyers are Wolverine Power Cooperative and Hoosier Energy. Michigan committed a $300 million grant, and the federal government backed the restart with a $1.52 billion loan guarantee. Rural cooperatives and public lenders have reasons of their own to preserve firm generation. Giving the technology industry credit for every restart in a region with growing data center demand understates those buyers' role and overstates what AI brought about.13
The states' side of the bargain
In 2016 the owner of the Clinton nuclear plant in Illinois was preparing to close it the following year. The reactor had been losing money, and a willing buyer for 20 years of carbon-free electricity had yet to appear. Illinois legislators chose to pay for keeping a working reactor. The money would come from electricity customers. When Meta signed a power agreement in June 2025, Clinton had operated for eight years beyond its scheduled closing date.14
Under the state program, electric utilities bought a credit for each qualifying megawatt-hour. Its price fell as wholesale power and capacity prices rose. Under the Illinois Power Agency's formula, the payment dropped from $9.38 per credit in the year starting June 2024 to $1.17 the following year and $1.02 in the program's final year. When the credits expire in May 2027, Meta's 20-year agreement for the clean-energy attributes of 1,121 megawatts is due to take over. Clinton has a federal operating license through April 2047, and Constellation expects to add 30 megawatts. Illinois customers paid to keep the reactor available to Meta. By the final year, their payment for each megawatt-hour had fallen to about a dollar.15
Pennsylvania faced a similar choice at Three Mile Island. In May 2019 Exelon announced that two bills had failed to advance in time for a June 1 fuel-purchasing deadline. The unit closed that September. By the time Microsoft signed in 2024, the contract had to support the cost of restarting the reactor as well as the cost of running it. Illinois bought years of continued operation and left a future customer a running machine. Pennsylvania let the decision pass to a future buyer. That buyer turned up five years later, by which time the route back to the grid also ran through a federal lender and PJM.16
In Georgia, the utility commission decided what Google could buy and who would receive the power. The commission's 2025 resource plan approved uprates at Vogtle Units 1 and 2 and contemplated a tariff for customers prepared to pay for additional nuclear output. Google subscribed to about 96 megawatts of uprates on Georgia Power's share of Vogtle and Hatch. The utility will put the electricity on its system for all customers. Google will receive the associated zero-emission credits. In October the Public Service Commission approved the Hatch project after approving the tariff. Georgia Power projects about $900 million in benefits to customers over the lives of the units.17
The order explains how a dollar from Google reaches a household in Savannah. From 2029, an enrollment payment reduces the amount of investment on which Georgia Power can earn a regulated return. Payments for the credits through 2028 are to be held on the books for customers until the next base rate case. After that, regulators can compare receipts with the amounts assumed in rates. A customer who wants to know what became of that $900 million projection will have somewhere to look. The commission has specified which payments the utility must account for and when.18
Wisconsin had a different problem. We Energies was already obliged to buy increasingly costly power from Point Beach. Oracle offered to absorb part of that expense. The companies estimated that the subscription would spare other customers about $300 million in fuel costs, subject to regulatory approval. There is no reactor upgrade behind that figure. The potential saving comes from changing who pays for power that the utility had contracted to buy anyway.19
Wisconsin also had to decide who would pay if the utility built for Oracle and the expected demand failed to arrive. In May, Wisconsin regulators issued a written order approving a retail tariff that requires very large customers to subscribe to resources bought or built to serve them. A customer that cuts its order generally remains liable for dedicated facilities unless the utility can put them to another use with commission approval. The credit protections have already been tested. WEC Energy Group reported in October that a credit downgrade at Oracle triggered a call for additional collateral. Oracle's cloud subsidiary and its parent posted it. That collateral gives the utility a claim it can draw on if the customer fails to pay. The projected fuel savings still depend on the subscription.20
Virginia allows customers to shoulder some risk earlier. State law lets Dominion recover approved costs of developing a small modular reactor before it has permission to build one. It caps this rider at $1.40 a month for a household using 1,000 kilowatt-hours. Dominion and Amazon signed a memorandum in 2024 to explore financing and development. At North Anna, the State Corporation Commission approved a development rider in 2025 and updated the costs in July 2026. Its order allows Dominion to come back by the end of 2027 with an application for state approval to build, another rider filing or a progress report. Virginia customers can begin paying for site engineering years before they know whether a reactor will occupy the site. Amazon's public agreement makes no commitment to purchase the output.21
New Jersey went further. Its legislature put a price on selling part of a future reactor's output directly to a data center. Under the Power NJ Act, signed in July, the state must seek at least 1,100 megawatts of new nuclear capacity. Before final approval a project must show a reasonable expectation of federal debt financing, where such financing is available, and the state must find a net benefit to ratepayers. If a project sells more than 1 percent of its generation to a single co-located user or under a direct power agreement with an end user, the megawatt-hours sold under that agreement lose eligibility for the state's Reliable Capacity Certificates. A developer negotiating with a data center can work out exactly which public revenue it would forgo.22
A buyer willing to invest during construction has another option. New Jersey allows a corporate buyer to negotiate a lower energy price if it contributes enough equity or assumes enough construction risk to bring its total contribution per megawatt-hour up to the statutory benchmark. In November the Board of Public Utilities was taking comments on what developers must disclose in their proposals. Nobody had won those 1,100 megawatts. But any technology company bidding for a share of a future reactor already knows what it can offer in exchange for cheaper electricity. It can put some of its own capital at risk before the first sale.23
The first customer for a new machine
In southern Ohio, some of Meta's money will reach a fuel supplier years before it reaches an electricity meter. On November 12, Oklo said Meta's advance payment had helped it secure fuel purchase agreements with Centrus. Deliveries are due to begin in 2029. Oklo says the contracts cover fuel for up to five of its Aurora reactors for several years, including the first phase of its proposed Ohio campus and other deployments. The Ohio campus has a target of 1,200 megawatts. The November contracts give Centrus a customer against which to finance new enrichment capacity. They also give Oklo a fuel delivery date around which it can plan construction.24
Oklo's agreement with the data center operator Switch envisages 12 gigawatts through 2044, ten times the proposed Ohio campus. The parties describe it as nonbinding. Meta's separate agreement with TerraPower funds early development of two 345-megawatt reactors and gives it rights to energy from as many as six more. TerraPower rates the first pair at 690 megawatts of steady output. Drawing on stored heat could raise that to 1,000 for more than five hours. A data center expecting 1,000 megawatts through the night would have to cover the difference when the store ran down.25
Google has taken a different route at Oak Ridge, Tennessee, where Kairos Power broke ground on its Hermes 2 demonstration plant in April. The wider Google–Kairos development agreement contemplates up to 500 megawatts. Hermes 2 accounts for up to 50, with first power targeted for 2030. The Tennessee Valley Authority (TVA) will buy the electricity and send it onto its system. Google will buy the clean-energy attributes through TVA for its data centers in Montgomery County, Tennessee, and Jackson County, Alabama. A customer in Alabama can help pay for the first reactor of its kind in Tennessee without moving a single server.26
Amazon is exploring a fleet of twelve 80-megawatt reactors with X-energy and American Electric Power at a former coal station in Indiana. In Washington, its partnership with Energy Northwest starts with four modules of the same design, with room for twelve. If both projects proceed, a manufacturer could supply the same machine to two utility systems. For Amazon, a second order could increase the value of the first by giving suppliers enough work to keep a production line running. The October Indiana agreement funds early work on that proposition. Counting its 960 megawatts today would assume the partners have already taken the decision they are paying to investigate.27
Table 2
When the next megawatts could arrive
| Sponsor target | Plant or portfolio | Expected milestone |
|---|---|---|
| 2027 | Crane / Microsoft | Restart could restore 835 MW |
| By 2028 | Constellation / Google | First of 890 MW of PJM uprates |
| Q1 2029 | Duane Arnold / Google and CIPCO | 615 MW restart across two buyers |
| 2030 | Hermes 2 / TVA and Google | Up to 50 MW from a new reactor |
| 2030–32 | Calvert Cliffs / Amazon | 190 MW of additional output |
| By 2034 | Vistra / Meta | Full 433 MW of PJM uprates |
Dates are company targets for additions to the grid. CIPCO is Central Iowa Power Cooperative. Sources: company announcements, federal orders and filings (notes 2, 4–6, 12 and 26).
Lawrence Berkeley National Laboratory's reference case puts U.S. data center electricity use at 649 terawatt-hours in 2030, within a range of 521 to 843. At an illustrative 90 percent capacity factor, the 1,513 megawatts of PJM uprates examined here would produce about 12 terawatt-hours in a full year. That is less than 2 percent of the national reference case, and some upgrades are scheduled years beyond 2030. The same increment looks quite different from Maryland. Amazon's deal there could increase the output of the state's only nuclear plant by more than a tenth.28
In Pennsylvania, the difference between keeping a reactor and recovering one will soon be visible at the generator. When Microsoft signed, the reactor stood idle. Since then the project has gained a federal loan and Eddystone's interconnection rights. If Crane returns to service in 2027, PJM will be able to count every megawatt it produces as supply the grid did not have the year before. For this winter, the November order keeps Eddystone on call through February 18.
Underlying data
Journal members can download the two AIxEnergy workbooks behind this article: the 43-record ledger of nuclear plants, restarts, uprates and reactor projects linked to data center buyers, and the policy index covering all 50 states and the District of Columbia.
Become a Journal memberNotes
- U.S. Department of Energy, "Energy Secretary Keeps Critical Generation Available in Mid-Atlantic," November 20, 2026 (order covering Eddystone Units 3 and 4, in effect November 21, 2026, through February 18, 2027), https://www.energy.gov/articles/energy-secretary-keeps-critical-generation-available-mid-atlantic-0. Constellation Energy Corporation and Constellation Energy Generation, LLC, Form 10-Q for the Quarter Ended September 30, 2026, filed November 9, 2026, note 3, "Capacity Interconnection Rights for Crane Clean Energy Center," and "Long-term Nuclear PPAs," https://www.sec.gov/Archives/edgar/data/1868275/000186827526000119/ceg-20260930.htm. U.S. Department of Energy, "Energy Department Closes Loan to Restart Nuclear Power Plant in Pennsylvania," November 18, 2025, https://www.energy.gov/articles/energy-department-closes-loan-restart-nuclear-power-plant-pennsylvania. ↩︎
- Constellation, September 2026 Form 10-Q, note 3 and "Long-Term Nuclear PPAs." Constellation Energy Generation, LLC, 195 FERC ¶ 61,162, paras. 10–13, 32–36 (June 1, 2026), docket no. ER26-2028-000, https://www.rtoinsider.com/wp-content/uploads/2026/06/FERC-ER26-2028-000-Crane-Eddystone-Waiver.pdf. Department of Energy, "Loan to Restart Nuclear Power Plant in Pennsylvania." ↩︎
- Constellation Energy, "Google and Constellation Announce Landmark Agreement to Bring 890 MW of New Nuclear Capacity to PJM Grid as Part of Long-Term Power Deal," October 6, 2026, https://www.constellationenergy.com/news/2026/10/google-and-constellation-announce-landmark-agreement-to-bring-890-mw-of-new-nuclear-capacity-to-pjm-grid.html. Vistra, "Vistra and Meta Announce Agreements to Support Nuclear Plants in PJM and Add New Nuclear Generation to the Grid," January 9, 2026, https://investor.vistracorp.com/2026-01-09-Vistra-and-Meta-Announce-Agreements-to-Support-Nuclear-Plants-in-PJM-and-Add-New-Nuclear-Generation-to-the-Grid. Constellation Energy, "Constellation and Amazon Announce 20-Year Power Purchase Agreement Adding 190 Megawatts of Nuclear Capacity at Calvert Cliffs," September 30, 2026, https://www.constellationenergy.com/news/2026/09/constellation-and-amazon-announce-20-year-power-purchase-agreement-at-calvert-cliffs.html. Constellation, September 2026 Form 10-Q, note 3 and "Long-Term Nuclear PPAs." ↩︎
- Constellation, "Google and Constellation Announce Landmark Agreement." Amanda Peterson Corio, "Why We're Backing America's Existing Nuclear Plants," The Keyword, Google, October 6, 2026, https://blog.google/company-news/why-were-backing-americas-existing-nuclear-plants/. Constellation, September 2026 Form 10-Q, note 3 and "Long-Term Nuclear PPAs." ↩︎
- Constellation, "Google and Constellation Announce Landmark Agreement." Constellation, "Power Purchase Agreement . . . at Calvert Cliffs." U.S. Department of Energy, "Energy Department Announces $5 Billion Loan to Boost Nuclear Power and Help Lower Costs in Illinois, Maryland, and Pennsylvania," October 27, 2026, https://www.energy.gov/articles/energy-department-announces-5-billion-loan-boost-nuclear-power-and-help-lower-costs. Constellation, September 2026 Form 10-Q, note 3 and "Long-Term Nuclear PPAs." ↩︎
- Vistra, "Vistra and Meta Announce Agreements." Vistra Corp., Form 10-K for the Year Ended December 31, 2025, filed February 27, 2026, item 7, "PJM Nuclear Power Purchase Agreements and Uprates" and "Comanche Peak Power Purchase Agreement," https://www.sec.gov/Archives/edgar/data/1692819/000169281926000006/vistra-20251231.htm. ↩︎
- AIxEnergy, Data Center Nuclear Power Plants, Restarts, Uprates & SMRs, project ledger NUC-INTEL-1.1.0, and U.S. State Nuclear Policies, Programs & Incentives, index NUC-STATE-POLICY-2026.2, both November 17, 2026, with accompanying AIxEnergy Map. Inventory count includes portfolio and development records. ↩︎
- Anna Haensch, Data Centers in 2026, presentation, University of Wisconsin–Madison, March 26, 2026, "Near-Future WI Data Centers Energy Needs," https://extension.wisc.edu/files/2026/05/Data_Centers_Wisconsin-Accessible.pdf. Oracle, "Oracle Announces Commitment to Absorb $300 Million in Rising Point Beach Energy Costs for Wisconsin Residents," October 2, 2026, https://www.oracle.com/news/announcement/oracle-announces-commitment-to-absorb-rising-point-beach-energy-costs-2026-10-02/. Danielle Kaeding, "Oracle Reaches Deal with We Energies That's Slated to Save Utility Customers $300M," Wisconsin Public Radio, October 6, 2026, https://www.wpr.org/news/oracle-deal-we-energies-utility-customers. WEC Energy Group, Inc., and Wisconsin Electric Power Company, Form 8-K, report dated August 14, 2026, item 1.01, https://www.sec.gov/Archives/edgar/data/107815/000078332526000095/wec-20260814.htm. The presentation lists the Port Washington campus as under construction. The August 2026 Point Beach agreement is subject to approval by the Public Service Commission of Wisconsin. ↩︎
- PJM Interconnection, L.L.C., 189 FERC ¶ 61,078, paras. 1, 10 (November 1, 2024), docket nos. ER24-2172-000 and ER24-2172-001, https://www.ferc.gov/sites/default/files/2024-11/20241101-3061_ER24-2172-000.pdf. Talen Energy Corporation, "Talen Energy Expands Nuclear Energy Relationship with Amazon," June 11, 2025, exhibit 99.1 to Form 8-K, https://www.sec.gov/Archives/edgar/data/1622536/000162828025030559/a20250611pressreleasebusin.htm. ↩︎
- Talen, "Nuclear Energy Relationship with Amazon." PJM Interconnection, L.L.C., "Proposed Tariff Revisions for Large Loads and Additional Compliance with Co-Location Order and Request for Extended 60-Day Comment Period," November 16, 2026, 1–3, docket no. ER27-531-000, https://www.pjm.com/-/media/DotCom/documents/ferc/filings/2026/20261116-er27-531-000.pdf. ↩︎
- Vistra, 2025 Form 10-K, item 7. ↩︎
- NextEra Energy, "NextEra Energy and Google Announce New Collaboration to Accelerate Nuclear Energy Deployment in the U.S.," October 27, 2025, https://www.investor.nexteraenergy.com/news-and-events/news-releases/2025/10-27-2025-203948689. U.S. Department of Energy, "Energy Department Closes $1.9 Billion Loan to Restart Duane Arnold Nuclear Plant," September 8, 2026, https://www.energy.gov/articles/energy-department-closes-19-billion-loan-restart-duane-arnold-nuclear-plant. NextEra Energy, Third Quarter 2025 Earnings Conference Call, prepared remarks, October 27, 2025, discussion of Duane Arnold Energy Center, https://www.investor.nexteraenergy.com/~/media/Files/N/NEE-IR/reports-and-fillings/quarterly-earnings/2025/Q3%202025/Final_Q3%202025%20Script%20vF.pdf. Andrew St. John, "Protecting Member Value While Preparing for the Future," Central Iowa Power Cooperative, November 2, 2026, https://cipco.net/news/protecting-member-value-while-preparing-future. ↩︎
- Holtec International, Palisades Nuclear Plant, project fact sheet, November 2026, "Decision to Restart," https://holtecinternational.com/wp-content/uploads/2026/11/Holtec-Palisades_Fact-Sheet_11-13-26.pdf. ↩︎
- Exelon Corporation, "Exelon Announces Early Retirement of Clinton and Quad Cities Nuclear Plants," June 2, 2016, exhibit 99.1 to Form 8-K, https://www.sec.gov/Archives/edgar/data/1109357/000119312516610539/d366527dex991.htm. Illinois Power Agency, Fiscal Year 2025 Annual Report (February 2026), 18, https://ipa.illinois.gov/content/dam/soi/en/web/ipa/documents/20260217-annual-report-fy25-final.pdf. Constellation Energy, "Constellation, Meta Sign 20-Year Deal for Clean, Reliable Nuclear Energy in Illinois," June 3, 2025, https://investors.constellationenergy.com/news-releases/news-release-details/constellation-meta-sign-20-year-deal-clean-reliable-nuclear. ↩︎
- Illinois Power Agency, Fiscal Year 2025 Annual Report, 18. Illinois Power Agency, Zero Emission Standard: Final Payment Calculation Notice of the Illinois Power Agency, delivery year June 1, 2026–May 31, 2027, June 10, 2026, 1, https://ipa.illinois.gov/content/dam/soi/en/web/ipa/documents/20260610-zec-final-pmt-calcs-dy-2026-2027.pdf. Constellation, "Constellation, Meta Sign 20-Year Deal." U.S. Nuclear Regulatory Commission, "Constellation Energy Generation, LLC; Clinton Power Station, Unit 1; License Renewal and Record of Decision," Federal Register, December 19, 2025, https://www.federalregister.gov/documents/2025/12/19/2025-23462/constellation-energy-generation-llc-clinton-power-station-unit-1-license-renewal-and-record-of. The renewed license expires April 17, 2047. ↩︎
- Exelon Generation, "Three Mile Island Unit 1 to Shut Down by September 30, 2019," May 8, 2019, https://www.constellationenergy.com/news/2019/three-mile-island-unit-1-to-shut-down-by-september-30–2019-aspx.html. Department of Energy, "Loan to Restart Nuclear Power Plant in Pennsylvania." Constellation, September 2026 Form 10-Q, note 3 and "Long-Term Nuclear PPAs." ↩︎
- Georgia Power, "Georgia Power Agreement with Google to Provide Approximately $900 Million in Projected Benefits for Customers and Advance Nuclear Energy in Georgia," September 21, 2026, https://www.georgiapower.com/news-hub/press-releases/agreement-with-google-provides-%24900-million-customer-benefits-advances-nuclear-energy.html. Georgia Public Service Commission, "Order Approving Georgia Power Company's Application for Approval of the 2026 Plant Hatch 1-2 Nuclear Extended Power Uprates ('EPU')," docket nos. 56002 and 56003, October 6, 2026, filed October 9, 2026, 2, https://services.psc.ga.gov/api/v1/External/Public/Get/Document/DownloadFile/229080/110003. ↩︎
- Georgia Public Service Commission, "Plant Hatch 1-2 Nuclear Extended Power Uprates," 2. ↩︎
- Oracle, "Commitment to Absorb $300 Million." We Energies, "We Energies Agreement with Oracle Expected to Save Customers Approximately $300 Million," October 2, 2026, https://news.we-energies.com/we-energies-agreement-with-oracle-expected-to-save-customers-approximately-300-million/. ↩︎
- Public Service Commission of Wisconsin, "PSC Overhauls We Energies' Data Center Tariff, Makes Improvements to Protect Existing Customers," docket no. 6630-TE-113, April 24, 2026, https://psc.wi.gov/Documents/PressReleases/04.24.2026PressRelease.PDF. WEC Energy Group, Inc., Form 10-Q for the Quarter Ended September 30, 2026, filed October 30, 2026, 47, 87, https://www.sec.gov/Archives/edgar/data/783325/000078332526000107/wec-20260930.htm. The commission discussed the tariff at its April 24, 2026, open meeting; WEC reports that the final written order was issued in May 2026. ↩︎
- Code of Virginia § 56-585.1:14(B)–(C) (2026), https://law.lis.virginia.gov/vacode/title56/chapter23/section56-585.1%3A14/. Dominion Energy, "Dominion Energy and Amazon to Explore Advancement of Small Modular Reactor (SMR) Nuclear Development in Virginia," October 16, 2024, https://investors.dominionenergy.com/news/press-release-details/2024/Dominion-Energy-and-Amazon-to-explore-advancement-of-Small-Modular-Reactor-SMR-nuclear-development-in-Virginia/default.aspx. Virginia State Corporation Commission, Status Report: Implementation of the Virginia Electric Utility Regulation Act Pursuant to §§ 56-596 B and 31-205 of the Code of Virginia, October 30, 2026, case nos. PUR-2024-00205 and PUR-2025-00196, https://rga.lis.virginia.gov/Published/2026/RD731/PDF. ↩︎
- Office of the Governor of New Jersey, "Governor Sherrill Signs Legislation Launching Procurement Process for New Nuclear Energy & Setting Strong Safeguards to Protect Ratepayers from Costs," July 13, 2026, https://www.nj.gov/governor/news/2026/approved/20260713a.shtml. Powering Opportunity, Workforce, and Energy Reliability for New Jersey Act, 2026 N.J. Laws ch. 42, §§ 3, 4(f), 6(a), 7(b) (July 13, 2026), https://pub.njleg.gov/Bills/2026/AL26/42_.HTM. ↩︎
- Power NJ Act, §§ 4(f), 6(a), 7(b). New Jersey Board of Public Utilities, "NJBPU Wants Your Input on Nuclear Energy Review Process," November 9, 2026, https://www.nj.gov/bpu/newsroom/2026/approved/20261109.html. ↩︎
- Oklo Inc., "Oklo, Centrus Secure Fuel Supply for Aurora Powerhouse Deployment in Ohio," November 12, 2026, https://investor.oklo.com/news/news-details/2026/Oklo-Centrus-Secure-Fuel-Supply-for-Aurora-Powerhouse-Deployment-in-Ohio/default.aspx. ↩︎
- Oklo Inc., "Oklo and Switch Form Landmark Strategic Relationship to Deploy 12 Gigawatts of Advanced Nuclear Power, One of the Largest Corporate Clean Power Agreements Ever Signed," December 18, 2024, https://oklo.com/newsroom/oklo-and-switch-form-landmark-strategic-relationship-to-deploy-12-gigawatts-of-advanced-nuclear-. TerraPower, "TerraPower and Meta Enter Agreement for 8 Natrium Advanced Nuclear Plants," January 9, 2026, https://www.terrapower.com/terrapower-announces-deal-with-meta. ↩︎
- Kairos Power, "Kairos Power Breaks Ground on Hermes 2 Demonstration Plant," April 17, 2026, https://www.kairospower.com/updates/kairos-power-breaks-ground-on-hermes-2-demonstration-plant. Tennessee Valley Authority, "Nuclear's New Horizons," August 18, 2025, https://www.tva.com/the-powerhouse/stories/nuclear-s-new-horizons. Amanda Peterson Corio, "Our First Advanced Nuclear Reactor Project with Kairos Power and Tennessee Valley Authority," The Keyword, Google, August 18, 2025, https://blog.google/company-news/outreach-and-initiatives/sustainability/google-first-advanced-nuclear-reactor-project-with-kairos-power-and-tennessee-valley-authority/. ↩︎
- Amazon, "Amazon Invests in Nuclear Energy Project Targeting Nearly 1 Gigawatt of Carbon-Free Energy for Indiana," October 19, 2026, https://www.aboutamazon.com/news/sustainability/amazon-nuclear-energy-indiana-x-energy-aep. American Electric Power, "AEP Partners with Amazon and X-energy to Explore Advanced Nuclear Energy in Indiana," October 19, 2026, https://www.aep.com/news/stories/view/12330/, identifying the former Breed Generating Station site in Sullivan County, Indiana. Energy Northwest, "Cascade Advanced Energy Facility," accessed November 21, 2026, https://www.energy-northwest.com/energy-projects/cascade-advanced-energy-facility/. ↩︎
- Sarah Josephine Smith et al., United States Data Center Energy Usage Report: 2025 Update (Berkeley, CA: Lawrence Berkeley National Laboratory, June 2026), https://eta.lbl.gov/publications/united-states-data-center-energy-2025. Vistra, "Vistra and Meta Announce Agreements." Constellation, "Google and Constellation Announce Landmark Agreement." Constellation, "Power Purchase Agreement . . . at Calvert Cliffs." ↩︎
Bibliography
- AIxEnergy. Data Center Nuclear Power Plants, Restarts, Uprates & SMRs. Project ledger NUC-INTEL-1.1.0. November 17, 2026.
- AIxEnergy. U.S. State Nuclear Policies, Programs & Incentives. Index NUC-STATE-POLICY-2026.2. November 17, 2026.
- Amazon. "Amazon Invests in Nuclear Energy Project Targeting Nearly 1 Gigawatt of Carbon-Free Energy for Indiana." October 19, 2026. https://www.aboutamazon.com/news/sustainability/amazon-nuclear-energy-indiana-x-energy-aep.
- American Electric Power. "AEP Partners with Amazon and X-energy to Explore Advanced Nuclear Energy in Indiana." October 19, 2026. https://www.aep.com/news/stories/view/12330/.
- Code of Virginia § 56-585.1:14 (2026). https://law.lis.virginia.gov/vacode/title56/chapter23/section56-585.1%3A14/.
- Constellation Energy. "Constellation and Amazon Announce 20-Year Power Purchase Agreement Adding 190 Megawatts of Nuclear Capacity at Calvert Cliffs." September 30, 2026. https://www.constellationenergy.com/news/2026/09/constellation-and-amazon-announce-20-year-power-purchase-agreement-at-calvert-cliffs.html.
- Constellation Energy. "Constellation, Meta Sign 20-Year Deal for Clean, Reliable Nuclear Energy in Illinois." June 3, 2025. https://investors.constellationenergy.com/news-releases/news-release-details/constellation-meta-sign-20-year-deal-clean-reliable-nuclear.
- Constellation Energy Corporation and Constellation Energy Generation, LLC. Form 10-Q for the Quarter Ended September 30, 2026. Filed November 9, 2026. https://www.sec.gov/Archives/edgar/data/1868275/000186827526000119/ceg-20260930.htm.
- Constellation Energy Generation, LLC. 195 FERC ¶ 61,162. Docket no. ER26-2028-000. June 1, 2026. https://www.rtoinsider.com/wp-content/uploads/2026/06/FERC-ER26-2028-000-Crane-Eddystone-Waiver.pdf.
- Constellation Energy. "Google and Constellation Announce Landmark Agreement to Bring 890 MW of New Nuclear Capacity to PJM Grid as Part of Long-Term Power Deal." October 6, 2026. https://www.constellationenergy.com/news/2026/10/google-and-constellation-announce-landmark-agreement-to-bring-890-mw-of-new-nuclear-capacity-to-pjm-grid.html.
- Dominion Energy. "Dominion Energy and Amazon to Explore Advancement of Small Modular Reactor (SMR) Nuclear Development in Virginia." October 16, 2024. https://investors.dominionenergy.com/news/press-release-details/2024/Dominion-Energy-and-Amazon-to-explore-advancement-of-Small-Modular-Reactor-SMR-nuclear-development-in-Virginia/default.aspx.
- Energy Northwest. "Cascade Advanced Energy Facility." Accessed November 21, 2026. https://www.energy-northwest.com/energy-projects/cascade-advanced-energy-facility/.
- Exelon Corporation. "Exelon Announces Early Retirement of Clinton and Quad Cities Nuclear Plants." June 2, 2016. Exhibit 99.1 to Form 8-K. https://www.sec.gov/Archives/edgar/data/1109357/000119312516610539/d366527dex991.htm.
- Exelon Generation. "Three Mile Island Unit 1 to Shut Down by September 30, 2019." May 8, 2019. https://www.constellationenergy.com/news/2019/three-mile-island-unit-1-to-shut-down-by-september-30–2019-aspx.html.
- Georgia Power. "Georgia Power Agreement with Google to Provide Approximately $900 Million in Projected Benefits for Customers and Advance Nuclear Energy in Georgia." September 21, 2026. https://www.georgiapower.com/news-hub/press-releases/agreement-with-google-provides-%24900-million-customer-benefits-advances-nuclear-energy.html.
- Georgia Public Service Commission. "Order Approving Georgia Power Company's Application for Approval of the 2026 Plant Hatch 1-2 Nuclear Extended Power Uprates ('EPU')." Docket nos. 56002 and 56003. October 6, 2026, filed October 9, 2026. https://services.psc.ga.gov/api/v1/External/Public/Get/Document/DownloadFile/229080/110003.
- Haensch, Anna. Data Centers in 2026. Presentation, University of Wisconsin–Madison, March 26, 2026. https://extension.wisc.edu/files/2026/05/Data_Centers_Wisconsin-Accessible.pdf.
- Holtec International. Palisades Nuclear Plant. Project fact sheet. November 2026. https://holtecinternational.com/wp-content/uploads/2026/11/Holtec-Palisades_Fact-Sheet_11-13-26.pdf.
- Illinois Power Agency. Fiscal Year 2025 Annual Report. February 2026. https://ipa.illinois.gov/content/dam/soi/en/web/ipa/documents/20260217-annual-report-fy25-final.pdf.
- Illinois Power Agency. Zero Emission Standard: Final Payment Calculation Notice of the Illinois Power Agency. Delivery year June 1, 2026–May 31, 2027. June 10, 2026. https://ipa.illinois.gov/content/dam/soi/en/web/ipa/documents/20260610-zec-final-pmt-calcs-dy-2026-2027.pdf.
- Kaeding, Danielle. "Oracle Reaches Deal with We Energies That's Slated to Save Utility Customers $300M." Wisconsin Public Radio, October 6, 2026. https://www.wpr.org/news/oracle-deal-we-energies-utility-customers.
- Kairos Power. "Kairos Power Breaks Ground on Hermes 2 Demonstration Plant." April 17, 2026. https://www.kairospower.com/updates/kairos-power-breaks-ground-on-hermes-2-demonstration-plant.
- New Jersey Board of Public Utilities. "NJBPU Wants Your Input on Nuclear Energy Review Process." November 9, 2026. https://www.nj.gov/bpu/newsroom/2026/approved/20261109.html.
- NextEra Energy. "NextEra Energy and Google Announce New Collaboration to Accelerate Nuclear Energy Deployment in the U.S." October 27, 2025. https://www.investor.nexteraenergy.com/news-and-events/news-releases/2025/10-27-2025-203948689.
- NextEra Energy. Third Quarter 2025 Earnings Conference Call. Prepared remarks. October 27, 2025. https://www.investor.nexteraenergy.com/~/media/Files/N/NEE-IR/reports-and-fillings/quarterly-earnings/2025/Q3%202025/Final_Q3%202025%20Script%20vF.pdf.
- Office of the Governor of New Jersey. "Governor Sherrill Signs Legislation Launching Procurement Process for New Nuclear Energy & Setting Strong Safeguards to Protect Ratepayers from Costs." July 13, 2026. https://www.nj.gov/governor/news/2026/approved/20260713a.shtml.
- Oklo Inc. "Oklo and Switch Form Landmark Strategic Relationship to Deploy 12 Gigawatts of Advanced Nuclear Power, One of the Largest Corporate Clean Power Agreements Ever Signed." December 18, 2024. https://oklo.com/newsroom/oklo-and-switch-form-landmark-strategic-relationship-to-deploy-12-gigawatts-of-advanced-nuclear-.
- Oklo Inc. "Oklo, Centrus Secure Fuel Supply for Aurora Powerhouse Deployment in Ohio." November 12, 2026. https://investor.oklo.com/news/news-details/2026/Oklo-Centrus-Secure-Fuel-Supply-for-Aurora-Powerhouse-Deployment-in-Ohio/default.aspx.
- Oracle. "Oracle Announces Commitment to Absorb $300 Million in Rising Point Beach Energy Costs for Wisconsin Residents." October 2, 2026. https://www.oracle.com/news/announcement/oracle-announces-commitment-to-absorb-rising-point-beach-energy-costs-2026-10-02/.
- Peterson Corio, Amanda. "Our First Advanced Nuclear Reactor Project with Kairos Power and Tennessee Valley Authority." The Keyword, Google, August 18, 2025. https://blog.google/company-news/outreach-and-initiatives/sustainability/google-first-advanced-nuclear-reactor-project-with-kairos-power-and-tennessee-valley-authority/.
- Peterson Corio, Amanda. "Why We're Backing America's Existing Nuclear Plants." The Keyword, Google, October 6, 2026. https://blog.google/company-news/why-were-backing-americas-existing-nuclear-plants/.
- PJM Interconnection, L.L.C. 189 FERC ¶ 61,078. Docket nos. ER24-2172-000 and ER24-2172-001. November 1, 2024. https://www.ferc.gov/sites/default/files/2024-11/20241101-3061_ER24-2172-000.pdf.
- PJM Interconnection, L.L.C. "Proposed Tariff Revisions for Large Loads and Additional Compliance with Co-Location Order and Request for Extended 60-Day Comment Period." Docket no. ER27-531-000. November 16, 2026. https://www.pjm.com/-/media/DotCom/documents/ferc/filings/2026/20261116-er27-531-000.pdf.
- Powering Opportunity, Workforce, and Energy Reliability for New Jersey Act. 2026 N.J. Laws ch. 42. July 13, 2026. https://pub.njleg.gov/Bills/2026/AL26/42_.HTM.
- Public Service Commission of Wisconsin. "PSC Overhauls We Energies' Data Center Tariff, Makes Improvements to Protect Existing Customers." Docket no. 6630-TE-113. April 24, 2026. https://psc.wi.gov/Documents/PressReleases/04.24.2026PressRelease.PDF.
- Smith, Sarah Josephine, Alex Hubbard, Alexander Newkirk, Mohan Ganeshalingam, Billie Holecek, Dale A. Sartor, Michael Mills, and Arman Shehabi. United States Data Center Energy Usage Report: 2025 Update. Berkeley, CA: Lawrence Berkeley National Laboratory, June 2026. https://eta.lbl.gov/publications/united-states-data-center-energy-2025.
- St. John, Andrew. "Protecting Member Value While Preparing for the Future." Central Iowa Power Cooperative, November 2, 2026. https://cipco.net/news/protecting-member-value-while-preparing-future.
- Talen Energy Corporation. "Talen Energy Expands Nuclear Energy Relationship with Amazon." June 11, 2025. Exhibit 99.1 to Form 8-K. https://www.sec.gov/Archives/edgar/data/1622536/000162828025030559/a20250611pressreleasebusin.htm.
- Tennessee Valley Authority. "Nuclear's New Horizons." August 18, 2025. https://www.tva.com/the-powerhouse/stories/nuclear-s-new-horizons.
- TerraPower. "TerraPower and Meta Enter Agreement for 8 Natrium Advanced Nuclear Plants." January 9, 2026. https://www.terrapower.com/terrapower-announces-deal-with-meta.
- U.S. Department of Energy. "Energy Department Announces $5 Billion Loan to Boost Nuclear Power and Help Lower Costs in Illinois, Maryland, and Pennsylvania." October 27, 2026. https://www.energy.gov/articles/energy-department-announces-5-billion-loan-boost-nuclear-power-and-help-lower-costs.
- U.S. Department of Energy. "Energy Department Closes $1.9 Billion Loan to Restart Duane Arnold Nuclear Plant." September 8, 2026. https://www.energy.gov/articles/energy-department-closes-19-billion-loan-restart-duane-arnold-nuclear-plant.
- U.S. Department of Energy. "Energy Department Closes Loan to Restart Nuclear Power Plant in Pennsylvania." November 18, 2025. https://www.energy.gov/articles/energy-department-closes-loan-restart-nuclear-power-plant-pennsylvania.
- U.S. Department of Energy. "Energy Secretary Keeps Critical Generation Available in Mid-Atlantic." November 20, 2026. https://www.energy.gov/articles/energy-secretary-keeps-critical-generation-available-mid-atlantic-0.
- U.S. Nuclear Regulatory Commission. "Constellation Energy Generation, LLC; Clinton Power Station, Unit 1; License Renewal and Record of Decision." Federal Register, December 19, 2025. https://www.federalregister.gov/documents/2025/12/19/2025-23462/constellation-energy-generation-llc-clinton-power-station-unit-1-license-renewal-and-record-of.
- Virginia State Corporation Commission. Status Report: Implementation of the Virginia Electric Utility Regulation Act Pursuant to §§ 56-596 B and 31-205 of the Code of Virginia. October 30, 2026. https://rga.lis.virginia.gov/Published/2026/RD731/PDF.
- Vistra Corp. Form 10-K for the Year Ended December 31, 2025. Filed February 27, 2026. https://www.sec.gov/Archives/edgar/data/1692819/000169281926000006/vistra-20251231.htm.
- Vistra. "Vistra and Meta Announce Agreements to Support Nuclear Plants in PJM and Add New Nuclear Generation to the Grid." January 9, 2026. https://investor.vistracorp.com/2026-01-09-Vistra-and-Meta-Announce-Agreements-to-Support-Nuclear-Plants-in-PJM-and-Add-New-Nuclear-Generation-to-the-Grid.
- We Energies. "We Energies Agreement with Oracle Expected to Save Customers Approximately $300 Million." October 2, 2026. https://news.we-energies.com/we-energies-agreement-with-oracle-expected-to-save-customers-approximately-300-million/.
- WEC Energy Group, Inc., and Wisconsin Electric Power Company. Form 8-K. Report dated August 14, 2026. https://www.sec.gov/Archives/edgar/data/107815/000078332526000095/wec-20260814.htm.
- WEC Energy Group, Inc. Form 10-Q for the Quarter Ended September 30, 2026. Filed October 30, 2026. https://www.sec.gov/Archives/edgar/data/783325/000078332526000107/wec-20260930.htm.